HAUPPAUGE PUBLIC SCHOOLS COMMUNITY PAGE
for BOND PROJECTS & CONSTRUCTION UPDATES
for BOND PROJECTS & CONSTRUCTION UPDATES
The Hauppauge Public Schools Bond Vote took place on
Tuesday, December 5th, 2023.
Click here to view the 2023 Bond Page with information on Project Scopes for each school, and other important information.
Update XIV - September 29, 2025
Completed projects: Bretton Woods Elementary roof, Pines Elementary parking lot expansion, Middle School Multipurpose Courts, High School Track and Tennis Courts.
On the Horizon: The next phase of our work has begun! This phase includes upgrades to our baseball and softball fields, as well as the high school multipurpose fields; improvements to ventilation and dehumidification systems throughout school buildings; and the replacement of all interior corridor doors and hardware across all buildings.
As always, we appreciate your support as we continue building safe, welcoming, and enriching spaces for our students, staff, and community.
Update XIII - August 21, 2025
We're excited to share the latest progress highlights on our bond project!
District-Wide: Upgrades to specific ventilation systems.
Bretton Woods Elementary: Localized roof renovations are nearly complete.
Pines Elementary: The expansion of the parking lot provides much-needed additional parking space.
Middle School: Paving for the multi-purpose courts for basketball, volleyball, and handball is complete. Fencing is installed, and sidewalk concrete has been poured. Additionally, improvements to the track and field area, including paving, are nearing completion.
High School:
Renovations to the Science Research Room are progressing, with final touches underway.
Track resurfacing is ongoing, including the jumping and shot put areas, along with upgrades to the area for discus throwing.
Synthetic turf infields are being constructed for both baseball and softball.
Since July, work has been underway to install two new synthetic multi-purpose turf fields.
Custom-colored benches, trash receptacles, and windscreens continue to be installed as materials arrive for the tennis and pickleball courts. The courts will be opened shortly to the community.
Thank you for your continued support as we enhance our schools for students, staff, and the community!
Update XII - July 2, 2025
We’re excited to share the latest progress on our bond project.
June Highlights
Construction is progressing at the high school on the tennis and pickleball courts. The courts are nearing completion: color coatings have been applied, court lines are being set, and only final touches remain before they can be opened to the community. Custom-colored benches, trash receptacles, and windscreens, aligned with Hauppauge’s branding, will be installed as materials arrive.
At the high school, work is progressing on the grass practice field, where the ground has been leveled.
July Highlights
Localized roof renovations at Bretton Woods.
The expansion of the parking lot at Pines will provide much-needed additional parking spaces.
Continued improvements district-wide:
High School: Resurfacing the track, jumping and shot put areas, upgrading the area for the discus throwing events, and constructing synthetic turf infields for both baseball and softball. Installation of two synthetic turf fields, enhancements to baseball and softball fields, renovation of the Science Research Room, and selective masonry repairs.
Middle School: New multi-purpose courts for basketball, volleyball, and handball, along with improvements to the track and field area.
District-Wide: Upgrades to specific ventilation systems.
Bond banners have been installed at each of our school buildings. Each banner includes a QR code that links directly to our website, providing easy access to more information about the bond project.
Thank you for your continued support as we enhance our schools for students, staff, and the community!
Update XI - May 23, 2025
Latest Developments!
We’re excited to share the latest progress on our bond project.
Phase 1 Timeline and Highlights:
May 2025: Construction continues at the high school with tennis and pickleball courts. The first section of the north retaining wall is complete, and trench drain installation is underway. Courts are expected to be completed by early July. Grass field work continues to progress.
Summer 2025:
Localized roof renovations at Bretton Woods.
Expand the parking area at Pines, providing much-needed additional parking spaces.
Continued athletic field improvements at the middle and high schools.
High School: resurfacing the track and jumping events and relocating and upgrading shot put and discus throwing events; construction of synthetic turf infields for baseball and softball.
Middle School: New multi-purpose courts for basketball, volleyball and handball, along with improvements to the track and field area.
Phase 2 Timeline and Highlights:
We’re pleased to share that Phase 2 has received formal approval from the New York State Education Department (NYSED). Bidding is now underway, with construction set to begin this summer.
June 2025: Solicit bids for Phase 2 work and Board of Education review and approval of the bids.
July 2025: Phase 2 construction begins.
High School: Installation of two synthetic turf fields, enhancements to baseball and softball fields, renovation of the Science Research Room, and selective masonry repairs.
District-Wide: HVAC upgrades
Thank you for your continued support as we enhance our schools for students, staff, and the community!
Update X - April 9, 2025
Exciting Progress Continues!
Phase 1 of our bond project is moving forward with significant progress made throughout March and early April. Here’s the latest update:
Phase 1 Timeline and Highlights:
February 2025: Construction began on high school tennis courts and grass practice field with the removal of soils, old tennis courts, and installation of drainage systems.
Progress: Compaction and grading continue around the tennis courts and grass practice field. Trenching for lighting conduits is nearly complete.
May 2025: Construction starts on MS handball, volleyball, and basketball courts.
Summer 2025:
Roof renovations (Wing II) at Bretton Woods.
Expand parking area at Pines, providing much-needed additional parking spaces.
Lighting upgrades (High School, Middle School, Pines and Forest Brook).
Continued athletic field improvements at the middle and high schools.
Phase 2 Timeline and Highlights:
May 2025: Anticipated New York State Education Department (NYSED) approval.
June 2025: Solicit bids for Phase 2 work and Board of Education review and approval of the bids.
July 2025: Phase 2 construction begins.
High School: Installation of two synthetic turf fields, enhancements to baseball and softball fields, renovation of the Science Research Room, and construction of an exterior security booth with associated access gates.
Middle School: Baseball/softball field upgrades.
District-Wide: Masonry repairs, HVAC upgrades, and district-wide classroom door and hardware replacement.
Thank you for your continued support as we enhance our schools for students, staff, and the community!
Update IX - March 7, 2025
Exciting Work Underway!
Construction has begun! Work at the high school tennis courts kicked off over winter break, marking the start of Phase 1 of our bond project. These improvements will enhance facilities across the District for students, staff, and the community.
Revised Phase 1 Timeline and Highlights:
February 2025: Construction begins on high school tennis courts and grass practice field
May 2025: Construction starts on MS handball, volleyball, and basketball courts
Summer 2025:
Roof renovations (Wing II) at Bretton Woods
Expand parking area at Pines, providing much-needed additional parking spaces
Lighting upgrades (High School, Middle School, Pines and Forest Brook)
Continued athletic field improvements at the middle and high schools.
Revised Phase 2 Timeline and Highlights:
Spring 2025: Anticipated New York State Education Department (NYSED) approval
May 2025: Solicit bids for Phase 2 work
June 2025: Board of Education review and approval of the bids
July 2025: Phase 2 construction begins.
High School: Installation of two synthetic turf fields, enhancements to baseball and softball fields, renovation of the Science Research Room, and construction of an exterior security booth with associated access gates
Middle School: Baseball/softball field upgrades
District-Wide: Masonry repairs, HVAC upgrades, and district-wide classroom door and hardware replacement.
Thank you for your continued support as we enhance our schools for students, staff, and the community!
Update VIII - November 26, 2024
The District has solicited bids from contractors for Phase 1 work. The Board of Education will review these bids at an upcoming meeting.
Phase 1 Timeline and Highlights:
January 2025: Construction begins on high school tennis courts and grass practice field
May 2025: Construction starts on MS handball, volleyball, and basketball courts
Summer 2025:
Roof renovations (Wing II) at Bretton Woods
Expand parking area at Pines, providing much-needed additional parking spaces
Lighting upgrades (High School, Middle School, Pines and Forest Brook)
Continued athletic field improvements at the middle and high schools.
Phase 2 plans have been submitted to NYSED for approval. Highlights include:
High School: Installation of two synthetic turf fields, enhancements to baseball and softball fields, renovation of the Science Research Room, and construction of an exterior security booth with associated access gates
Middle School: Baseball/softball field upgrades
District-Wide: Masonry repairs, HVAC upgrades, and district-wide classroom door and hardware replacement.
Phase 2 Timeline:
Spring 2025: Anticipated New York State Education Department (NYSED) approval
May 2025: Solicit bids for Phase 2 work
June 2025: Board of Education review and approval of the bids
July 2025: Phase 2 construction begins.
Thank you for your continued support as we enhance our schools for students, staff, and the community!
Update VII - October 24, 2024
Since our last update on September 24, 2024, we are pleased to share that the District has officially received approval for the Phase 1 Plan from the New York State Education Department (NYSED). The plan, originally submitted on March 11, 2024, will now move forward with the following key projects:
Improvements to the athletic fields at the high school and middle school
Roof renovations (“Wing II”) at Bretton Woods
Expanding parking area at Pines, providing much-needed additional parking spaces
Upgrading lighting in various areas across the District
With this approval in hand, we will begin the process of soliciting bids for these projects. The Board of Education will review the bids at an upcoming meeting.
Revised Timeline for Phase 1:
November 2024: Bond Sub-Committee Meeting
January 2025: Start construction on the high school tennis courts and grass practice field
May 2025: Begin middle school court construction (handball/volleyball/basketball),
Summer 2025: Roof renovations (“Wing II”) at Bretton Woods, expanding parking at Pines, lighting upgrades, and continued athletic field improvements at the middle and high schools.
Update VI - September 24, 2024
Since our last update on August 22, 2024, the District has continued regular meetings with our architect and construction manager to keep things moving forward. We're excited to share that the Phase 1 Plan, which we submitted to the State Education Department (NYSED) on March 11, 2024, is in the final approval stage, and we anticipate receiving building permits within the next three weeks.
Phase 1 will include:
Improvements to the athletic fields at the high school and middle school
Roof renovations (“Wing II”) at Bretton Woods
Expanding parking at Pines
Upgrading lighting in various areas across the District
Once we have NYSED's final approval and building permits, we will proceed with soliciting bids for the work, which the Board of Education will consider at an upcoming meeting.
Revised Timeline for Phase 1:
November 2024: Bond Sub-Committee Meeting
December 2024: Start construction on the high school tennis courts and grass practice field
March 2025: Begin middle school court construction and track resurfacing
Summer 2025: Roof renovations (“Wing II”) at Bretton Woods, expanding parking at Pines, lighting upgrades, and continued athletic field improvements at the middle and high schools.
Update V - August 22, 2024
Since our last update on July 22, 2024, the District has continued holding bi-weekly meetings with our architect and construction manager to ensure steady progress. We are pleased to announce that the Phase 1 Plan, submitted to the State Education Department (NYSED) on March 11, 2024, is currently "under review" by the state’s architectural review committee.
Phase 1 includes key upgrades such as athletic field improvements at the high school and middle school, roof renovations at Bretton Woods, site work and parking expansion at Pines, and selected lighting enhancements throughout the District.
As per state regulations, school districts are required to obtain final approval from NYSED before proceeding with bids or commencing construction. We remain hopeful that by our next update, we will have received approval and can provide details on the next steps.
Update IV - July 22, 2024
Since our last update on May 22, 2024, the District has been diligently holding bi-weekly meetings with our architect and construction manager.
We are currently awaiting approval for the Phase 1 Plan submitted to the State Education Department (NYSED) on March 11, 2024. Phase 1 encompasses athletic field updates at the high school and middle school, roof renovations at Bretton Woods, site work and parking expansion at Pines, and selected lighting improvements throughout the District.
Unfortunately, school districts cannot proceed with bids or commence construction until final approval is granted by NYSED. At present, the state’s architectural review committee is evaluating projects submitted on February 13, 2024. We remain optimistic that by next month’s update, we will be able to share the approval status and outline the next steps.
Update III - May 22, 2024
Since the last update on March 22, 2024, the District has conducted interviews for the Construction Manager firm which will oversee the construction projects included in each phase of the Bond. A recommendation will be submitted for Board of Education consideration at the next meeting on June 4, 2024.
The District still awaits approval for the plan submitted to the State Education Department for Phase 1. The first phase includes athletic field updates at the high school and middle school, roof work at Bretton Woods, site work and parking expansion at Pines, and select lighting throughout the District.
Update II - March 22, 2024
This month, the “Phase 1” project scope was submitted to the New York State Education Department (NYSED) for review and approval.
While we await approval, the District will receive topography and survey results to prepare for the pre-design for “Phase 1.” The District will continue to meet with our Architects for pre-planning.
An RFP (Request for Proposal) for a Construction Manager is underway, and we anticipate submitting a firm for Board of Education consideration by our next update.
Update I - February 22, 2024
The project's overall scope has been categorized into three phases of construction, which will spread the work out over the next few years. The first phase includes athletic field updates at the high school and middle school, roof work at Bretton Woods, Pines site work and parking expansion, and select lighting throughout the district. “Phase 1” will be submitted to the New York State Education Department (NYSED) for review and approval in the upcoming weeks.
Upon NYSED’s approval of the projects, the district’s architect and construction management team will finalize bids/construction costs for the work in “Phase 1.” Once the District approves the bids, construction will begin. Currently, the District anticipates breaking ground on “Phase 1” projects in the summer of 2024.
Please click on the links below for important information.
Hauppauge Community Subcommittee Survey
Hauppauge Bond Subcommittee Roster
Hauppauge Project Scopes - All Schools
Hauppauge Bond Vote Presentation