Canvas Implementation Timeline
CANVAS Implementation Timeline - All Text Format
CANVAS Implementation Timeline - All Text Format
Nov-Dec 2016
- License Canvas
- Develop Canvas Implementation Plan
- Explore Canvas training options
- Identify Canvas Trailblazers and provide access to training
- Begin CETL Staff training
Jan 2017
- Put technical aspects of Canvas into place – SSO, SIS, branding
- Begin Admin training
- Continue CETL Staff training
- Begin collecting migration requests
- 1/31 – launch website
Feb 2017
- Create Sandbox courses for faculty
- Provide faculty access to Canvas Camp training course and other self-help training materials
- Offer Canvas Overview Sessions
- Process migration requests - prioritize SU2017 M1 and full sem courses
Mar 2017
- 3/1 – All SU2017 M1 and full sem courses moved to Canvas
- Offer expanded training and Course Clean-Up sessions - prioritize SU2017 M1 and full sem courses
- Process migration requests - prioritize SU2017 M2
Apr 2017
- Offer expanded training and Course Clean-Up sessions – prioritize SU2017 M1 and full sem courses
- Process migration requests - prioritize SU2017 M2
- 4/17 – Provide student access to Canvas Camp course
- 4/24 – SU2017 M1 courses staged
May 2017
- 5/1 – open early access SU2017 M1
- 5/8 – SU2017 M1 begins
- 5/8 – All SU2017 M2 courses moved to Canvas
- Offer expanded training and Course Clean-Up sessions
- Process migration requests – Prioritize FA2017
Jun 2017
- Offer expanded training and Course Clean-Up sessions
- Process migration requests – Prioritize FA2017 M1
- 6/11 – SU2017 M2 courses staged
- 6/18 – open early access SU2017 M2
- 6/25 – SU2017 M2 begins
- 6/30 – BB is retired
Jul 2017
- Offer expanded training and Course Clean-Up sessions
- Process migration requests – prioritize FA2017 M1 and full sem courses
Aug 2017
- Offer expanded training and Course Clean-Up sessions
- Process migration requests
- 8/14 – FA2017 M1 and full sem courses staged
- 8/21 – open early access FA2017 M1
- 8/28 – FA2017 M1 and full sem begins
FALL 2017
- Continue processing migration requests for all remaining courses
- Offer expanded training and Course Clean-Up sessions
- Set target dates for Spring 2018 courses
This timeline may be adjusted as the project proceeds. The current version may always be viewed on this website.
This timeline may be adjusted as the project proceeds. The current version may always be viewed on this website.
For information, contact twilson@francis.edu.