Dawson-Boyd

DISTRICT BUILDING PROJECT

WORK CONTINUES

January 13, 2021

By working outside of school hours, contractors were able to cut out concrete inside the school for our remodel project. As you can see, yes, there were wires cut. But since contractors worked outside of school hours, a minimal disturbance was made to the school day. Thanks to them, as well our teachers/staff and students for being flexible during the past day and a half so that this could be accomplished!


Also, roof decking is going up on the elementary addition!


Carousel imageCarousel imageCarousel image

Construction

January 8, 2021

Construction continues to move forward. The HS first floor bathrooms have been demoed and are ready for the remodel to begin and the elementary addition is slated to be enclosed by the beginning of February.

Carousel imageCarousel imageCarousel image

Project Footprint

December 21, 2020

Construction continues on the district building and remodeling project. Electrical panels are being updated and metal studs are going up, forming a skeleton of what's to come! Aerial photos courtesy of Ryan Lund.

Carousel imageCarousel imageCarousel imageCarousel imageCarousel image

Going Up

December 10, 2020

With very favorable weather, construction continued with footings and foundations on the community center addition. However, structural steel has also started to go up on the elementary addition.

Carousel imageCarousel imageCarousel imageCarousel image

A lOok From above

November 23, 2020

It's difficult to see from the street, but there's been a lot of progress on the school's building project. All of the deep footings have been formed & poured with the shallow footings being next. After Dec. 1, you should be seeing steel structure going up. Thank you to Ryan Lund for the drone pictures.

Carousel imageCarousel imageCarousel image

MORE Progress

September 24, 2020

Construction for the addition/remodel project is moving along nicely. Excavation of the STEAM room and footings have been completed. Soil correction and excavation for the parking lot and elementary addition are also wrapping up. The footings for the elementary addition will be next.

Carousel imageCarousel imageCarousel imageCarousel image

Progress

September 16, 2020

Stevens Elementary is seeing progress on our new STEAM Room on the northeast corner! STEAM education is an approach to learning that uses Science, Technology, Engineering, the Arts and Mathematics as access points for guiding student inquiry, dialogue, and critical thinking. Can't wait to see the things we can discover!

Carousel imageCarousel imageCarousel imageCarousel image

Construction

August 25, 2020

Construction is ramping up on the Dawson-Boyd remodel/addition project. Work area fencing and signage was installed this week while the elementary building tie-in and new electrical service moved forward.



Carousel imageCarousel imageCarousel imageCarousel image

DeMO & PREP

August 17, 2020

Even though the district is making plans for Covid-19 decisions, the remodel and addition project are moving forward. This week, contractors started demolishing the area by the pool doors for the elementary addition tie-in.



Carousel imageCarousel imageCarousel imageCarousel image

Construction

July 15, 2020

As summer hits full stride, evidence of construction is happening at Dawson-Boyd. Brent Moseng Construction is building the custodial garage as L & S Electrical of Springfield, MN, is getting a jump start on the building project for the new elementary addition. Reminder to parents of young children...please have the conversation that it is ok to see what is going on from outside the cones...but do not enter the construction site. As the summer winds down and the beginning of school gets closer, more machinery and "action" will be taking place.



Carousel imageCarousel image

Bids Approved

June 8, 2020

The Dawson-Boyd School Board approved bid packages at last night's (June 8) Board meeting for the remodel/addition project. All bids came in under budget which allowed the district to add in all of it's alternates, which also came in under budget. Once plans are approved and finalized by the State of Minnesota, dirt work will begin. The projected start is August 2020.

View Plans


Carousel imageCarousel imageCarousel imageCarousel image

Making More Room

March 27, 2020

Dawson-Boyd FD members burn down the former Steve and Marlys O'neal house to make room for the custodial garage and for future parking.


Carousel imageCarousel imageCarousel imageCarousel image

Greenhouse MOVED

January 8, 2020

The greenhouse was moved to its final place to make room for the elementary addition.


Carousel imageCarousel imageCarousel imageCarousel image

Burn Then Build

December 14, 2019

Fire fighters from Dawson, Boyd, Bellingham, and Madison teamed up in training before burning down the former Carol Phillips home to make room for the upcoming Dawson-Boyd school addition. Chip Lohmiller, former kicker for the MN Vikings. was on hand as an instructor for the MN Firemen's Association. After the required 10 days, debris/ash will be removed and the area will be brought to grade.


Carousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel image

Greenhouse Pad

November 19, 2019

The new pad for the greenhouse was prepared this past Tuesday, making it ready for the greenhouse later this winter. This will allow room for the new elementary addition.


Carousel imageCarousel image

Making Progress

November 6, 2019

Continued progress on the preparing for construction behind the school. The foundation/basements of the former tan house and Brad Krugerud house are being dug out and filled in. The green house on the east side of the gym will be torn down, removed and filled in next with the former Carol Phillips house being burned down by the Dawson FD (for training) on Dec. 14. The greenhouse will be moved to the area where the Krugerud house was. This will open the entire area behind the school for the elementary addition and additional parking.


Carousel imageCarousel image

DIRT WORK

October 28, 2019

The process of digging out and filling in the foundations/basements north of the school has begun. Please be aware that as this process goes on, side roads may be closed temporarily as this process goes on.


Carousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel image

On The MOVE

October 18, 2019

The School House (located just outside the "Pool Doors" on the North side of the school) was moved to clear even more space for the new addition.


Carousel imageCarousel imageCarousel image

SITE PREP

October 8-11, 2019

Site preparation continues for the Dawson-Boyd building project. Trees are being cleared to allow room for moving of structures and construction equipment. Once construction is completed, new trees will be planted to suit the landscape.

Carousel imageCarousel imageCarousel imageCarousel imageCarousel image

CLEARING SPACE

September 28, 2019

Dawson's FD used a controlled burn/training of Brad Krugerud's former house to unofficially begin the Dawson-Boyd building and remodel project.

The Unofficial Start of the Building ProjectThe Unofficial Start of the Building ProjectThe Unofficial Start of the Building ProjectThe Unofficial Start of the Building ProjectCarousel imageThe Unofficial Start of the Building Project