Bond Background:

On February 5, 2008, the Windsor voters passed a $50 Million school facilities bond.  In April of 2015 Windsor Unified School District (WUSD) contracted with Van Pelt Construction Services (VPCS) to provide Program and Construction Management Services. Construction notices for all projects at WUSD will be posted below.  Links to progress photos can also be found on this page. One of the most important aspects of construction on school campuses is safety.  All parties involved with this bond program understand the dynamics of working on K-12 campuses.  Student and Faculty safety will always be at the forefront of decision making. This website will be the best place for staff, students and public to get information related to ongoing construction projects. Inconvenience is an unfortunate byproduct of construction and we apologize in advance for any inconvenience construction may cause.  Eric Van Pelt is VPCS Sr. Project Manager, overseeing the construction at WUSD. Should you have any questions, comments or concerns please feel free to contact Eric at Eric@vpcsonline.com.


      WUSD Partners
  • ATI Architecture, Dublin California
  • Ridgeview Builders, Santa Rosa California
  • FRC Inc., Windsor and Petaluma, California
  • GeoCon Consultants, Fairfield California
  • Bruce Mansell Inspection, Sebastopol California


Project Description: 

Brooks Elementary School-  Phase I of this project includes relocation of six portable buildings, upgrade of electrical infrastructure, upgrade of water and sewer infrastructure and installation of temporary fencing for Phase II.

Phase II of this project includes upgrades to bus turnaround, upgrades to ADA parking stalls, construction of new ADA compliant walkway across Natalie drive, construction of a new two story classroom building and construction of a new parking lot/parent drop off area.

Windsor Oaks Academy-  Phase I of this project includes the relocation of seven portable buildings and reconfiguration of the school parking lot.  

Phase II of this project includes the construction of a new two story classroom building.



Construction Notices:

Brooks Elementary:

Week of 6/22: This week, the following processes will be happening on site; site demolition, disconnecting power to the portable buildings, rough grading, and surveying and layout.

Week of 7/6: This week, the following processes will be happening on site; cutting pads to grade, relocating portable buildings and trenching underground utilities.

Week of 7/13: This week, the portable buildings have been moved to back of site, underground trenching to be completed this week.

Week of 7/20: This week, the new buildings are relocated, connecting utilities is in process, the addition portable is being delivered on site 7/24, and the final preparations for paving are taking place.

Week of 7/27: This week, final underground utility work is being completed, paving will take place on Friday and classroom contents are being moved back into portable classrooms.

Week of 8/3: This week, building connections are being finished, ramps are being installed onto the portables, patch paving will take place, and the buildings will be painted.

Week of 8/10: This week, the fire alarm system is being tested, power is on in the portable buildings, guards for the HVAC units are being installed, and plumbing connections are being finished.

Windsor Oaks Academy:

Week of 6/22: This week, the following processes will be happening on site; site demolition, disconnecting power to the portable buildings, rough grading, and surveying and layout.

Week of 7/6: This week, the following processes will be happening on site; setting grade and compacting for the building pads and for the parking lot, decommissioning portable buildings and prepping to move them.

Week of 7/13: This week, final grades are being set, and underground utility work is ongoing.

Week of 7/20: This week, final paving preparations are taking place, paving is beginning, and the relocation of the portable buildings is beginning. 

Week of 7/27: This week, the portable buildings are being moved, and underground gas and sewer/water connections are being completed.

Week of 8/3: This week, the portable buildings are being connected, concrete pouring is taking place, paving will occur, and there will be electricians on site doing work.

Week of 8/10: This week, power will be on in the portable buildings, the fire alarm system is being tested, paving is finishing, the fences are being removed around the parking lot, the parking lot is being striped, and the ramps and handrails to the portables are being worked on.

Windsor Middle School: 

Week of 8/3: Two portable buildings are being delivered and placed.

Windsor High School:

Week of 8/3: One portable building is being delivered and placed.


Shutdown Notices:

None at this time.



CONTACT INFORMATION:

NameCompanyProjectContact Info
Eric Van Pelt       VPCS Windsor Oaks Academy and Brooks Elementary School eric@vpcsonline.com
Holly MaddoxVPCSWindsor Oaks Academy and Brooks Elementary Schoolholly@vpcsonline.com
Robert CumminsWUSDWindsor Oaks Academy and Brooks Elementary Schoolrcummins@wusd.org
Tom LangerRidgeview BuildersBrooks Elementary School 
Rup ChandATIWindsor Oaks Academy and Brooks Elementary School 
Frank RuggirelloFRC, Inc.Windsor Oaks Academy 



WOA & Brooks Schedule