Project Timeline

Technical Upgrade 

April - May
Retrofit current state to 9.2 platform

May - September
Testing and defect management

September 23 & 24
Upgrade production system

September 25
Go-live

Functional Upgrade

April
Charter initiation

May - August
Analyze and Design

October - June
Iterative releases of functionality