FFA Greenhouse

2010-2012 Project Progress
 
Mr. Jim McGuire
Parent Volunteer Construction Manager
 
Evan Medvec
Ag Student Construction Manager
 
Saline Ag Students,
PTO Parents
Kevin's Landscape
 
UPDATE:
THE GREENHOUSE IS ALMOST DONE!
  • Structure is up
  • Electrical is in.
  • Heating/Cooling system is in
  • Benches are built
  • Rain Barrel water conservation system installed
Goals:
  • Complete drip irigation system installation
  • Test all systems by OCT 15, 2012
  • Have first flower crop in for Spring 2013

COMMUNITY PARTNERS
 


  
 
 