RE0455u

Project management in removing barriers (4 elevators)

1,00973,20973,20738,2632,1375,86
Management of the works described in the implementation plan for the elimination of architectural barriers in a building or premises with four lifts. Includes: one weekly visit at work, drafting additional documents, control of construction certificates, certified emission end of the work and drafting of the final document of the project work, containing the final state of the works.
%01a%Ancillary costs of labor0,024,35
%02%indirect costs0,039,23
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
RE0186uFurther work on the project manager4,7368,88325,94260,2611,83
RE0187uVisit the work of director execution4,7368,88325,94260,2611,83
MOU0063hTechnical. Professional level III (Source: IVE). / More information2,7322,0060,1160,112,73
MOU0066hCoordinator / Technician. Professional Level II (Source: IVE). / More information2,8725,0071,6571,652,87
MOU0081hDirector / Technician. Professional Level II (Source: IVE). / More information2,8730,0085,9885,982,87
REU0763uAverage cost of premiums for professional liability insurance, per 1,000 currency units or technical fees fraction.1,0050,0050,00
REU0762uAverage cost of fees and contributions to the management and visa proceedings in a professional for every 1,000 currency units or technical fees fraction.1,0040,0040,00
written by Joaquim Iborra Posadas
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 18/03/2018
zone València
observations: Partides relacionades: RE0452, RE0453, RE454, RE0455.
..........