REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0448u

Writing project on removing barriers building (one elevator)

1,00363,44363,44241,3227,3266,40
Writing implementation plan for the elimination of architectural barriers on a building with one elevator. Consisting of technical visits for data collection, the current uprising, study and assessment of existing needs and approach of the work aimed at the elimination of architectural barriers. Includes shift a maximum distance of 20 km, memory document specification, budget and all necessary plans in order to put into action the works.
%01a%Ancillary costs of labor0,020,65
%02%indirect costs0,033,68
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
RE0174uDedication of a technical report writing1,0035,7035,7034,004,00
RE0175uDedication of a technical specification writing1,0027,3027,3026,003,00
RE0176uDedication of a technical drafting budget1,0035,7035,7034,004,00
RE0177uDedication of a technical drawing of a graphic section1,0034,1334,1332,504,00
RE0178uData acquisition and leverage current state (1 UI)1,0088,1288,1275,669,66
MOU0066hTechnical coordinator1,0012,5012,5012,501,00
MOU0081hTechnical director1,0020,0020,0020,001,00
RE0153uDisplacement of a technician (distance intervals of 10 km or fraction)2,007,8315,666,660,66
REU0763uAverage cost of premiums for professional liability insurance, per 1,000 currency units or technical fees fraction.1,0050,0050,00
REU0762uAverage cost of fees and contributions to the management and visa proceedings in a professional for every 1,000 currency units or technical fees fraction.1,0040,0040,00
written by Joaquim Iborra Posadas
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 30/04/2014
zone València
observations: Notes de l'autor?
..........
Validated by ?
profile ?
Validated date 00/00/0000
observations: Notes del validador?