CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0439u

Fees integral rehabilitation technicians (10 IU)

1,004.958,384.958,383.735,53352,9375,34
Technical work for the complete renovation of a building with 10 units in operation inspection. Consisting of technical visits for data collection, the current uprising, study and assessment of the deficiencies identified and approach of the work aimed at the rehabilitation of the building renovation project drafting, drafting the necessary annexes, writing health and safety study, drafting of study on waste management, construction management, performance management, coordination of health and safety coordination and management of waste. Includes: displacement in a metropolitan area to a maximum distance of 20 km.
%01a%Ancillary costs of labor0,02
%02%indirect costs0,03
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
RE0171uDrafting building rehabilitation project (10 IU)1,002.533,702.533,702.176,15220,95
RE0417uConstruction management of comprehensive rehabilitation (10 IU)1,00705,48705,48496,9342,63
RE0443uExecution of comprehensive rehabilitation (10 IU)1,00705,48705,48496,9342,63
RE0422uHealth and Safety Study of comprehensive rehabilitation (10 IU)1,00226,95226,95138,8510,00
RE0426uStudy Waste Management comprehensive rehabilitation (10 IU)1,00179,48179,4882,657,10
RE0435uHealth and Safety Coordination comprehensive rehabilitation (10 IU)1,00427,81427,81261,3722,52
RE0430uWaste Management Coordination comprehensive rehabilitation (10 IU)1,00179,48179,4882,657,10
observations:
Not included under this heading the cost of coves and laboratory tests to run, if it is necessary to write this project. It is considered independent inspection unit each of the following: every home regardless of the surface; premises for commercial use, warehouse, garage or any other use other than housing on the same level and up to 200 m² of floor area or fraction. It cosidera comprehensive rehabilitation works aimed designed to achieve structural adjustment funcinal of the building.
written by Joaquim Iborra Posadas
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 30/04/2014
zone València
observations: Partides idèntiques en la formulació: RE0438, RE0439, RE0440, RE0441.
..........
Validated by ?