CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0438u

Writing project management and renovation building (1 UI)

1,005.491,365.491,364.268,99191,5077,74
Writing project studies and project management for the renovation of a building with intervention in the first inspection unit, consisting of technical visits for data collection, the current uprising, study and assessment of the deficiencies identified and description of the solution for the rehabilitation of the building renovation project drafting, drafting of the annexes required, drafting health and safety study, drafting of study on waste management, construction management, address execution, coordination of health and safety coordination and management of waste. Includes visits and travel.
%01a%Ancillary costs of labor0,02
%02%indirect costs0,03
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
RE0173uDrafting building rehabilitation project (1 UI)1,002.927,742.927,742.537,35117,00
RE0416uDirector of the rehabilitation works (1 UI)1,00667,68667,68484,0021,00
RE0442uExecution rehabilitation (1 UI)1,00667,68667,68484,0021,00
RE0421uStudy of Safety and Health Rehabilitation (1 UI)1,00268,39268,39167,327,00
RE0425uStudy Waste Management Rehabilitation (1 UI)1,00216,76216,76118,165,00
RE0434uOccupational Safety and Health Coordination Building renovation (1 UI)1,00457,47457,47305,0013,00
RE0429uWaste Management Coordination rehabilitation building (1 UI)1,00285,64285,64173,167,50
observations:
Not included under this heading the cost of coves and laboratory tests to run, if it is necessary to write this project. It is considered independent inspection unit each of the following: every home regardless of the surface; premises for commercial use, warehouse, garage or any other use other than housing on the same level and up to 200 m² of floor area or fraction. Considers rehabilitation works aimed at adapting the structural and functional construction of the building.
written by Joaquim Iborra Posadas
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 19/03/2018
zone València
observations: Partides idèntiques en la formulació: RE0438, RE0439, RE0440, RE0441.
..........