CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0430u

Waste Management Coordination comprehensive rehabilitation (10 IU)

1,00179,48179,4882,657,1046,05
Work relating to Waste Management Coordination according to the study prepared for the works carried out in the implementation plan for a comprehensive rehabilitation or local building inspection units 10, in accordance with s 'established in Royal Decree 105/2008, February 1, 2008, the Ministry of the Presidency, which regulates the production and management of construction and demolition waste.
%01a%Ancillary costs of labor0,021,65
%02%indirect costs0,035,18
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
MOU0063htechnical2,2010,0022,0022,002,20
MOU0064hTechnical assistant2,308,0018,4018,402,30
MOU0066hTechnical coordinator1,3012,5016,2516,251,30
MOU0081hTechnical director1,3020,0026,0026,001,30
REU0763uAverage cost of premiums for professional liability insurance, per 1,000 currency units or technical fees fraction.1,0050,0050,00
REU0762uAverage cost of fees and contributions to the management and visa proceedings in a professional for every 1,000 currency units or technical fees fraction.1,0040,0040,00
profile ?
company: ?
update 00/00/0000
zone ?
observations: Partides idèntiques en la formulació: RE0429, RE0430, RE0431, RE0432.
..........