REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0417u

Construction management of comprehensive rehabilitation (10 IU)

1,00705,48705,48496,9342,6370,44
Construction management in developed implementation plan for building 10 units or local inspection. Includes: one weekly visit at work drafting of additional documents that may be required to detail any element of work, monitoring of work certifications, issuing the final certificate of work and drafting of the final document of the project work , containing the final state of the works.
%01a%Ancillary costs of labor0,024,34
%02%indirect costs0,039,21
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
RE0186uSite visit of the project manager (distance <20 km)10,5036,66384,93279,9327,93
MOU0063htechnical3,5010,0035,0035,003,50
MOU0066hTechnical coordinator5,6012,5070,0070,005,60
MOU0081hTechnical director5,6020,00112,00112,005,60
REU0763uAverage cost of premiums for professional liability insurance, per 1,000 currency units or technical fees fraction.1,0050,0050,00
REU0762uAverage cost of fees and contributions to the management and visa proceedings in a professional for every 1,000 currency units or technical fees fraction.1,0040,0040,00
observations:
Works included in the Ley 38/1999 of 5 November, of Ordenación of edificiación.
written by Joaquim Iborra Posadas
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 7/11/2016
zone València
observations:
..........
Validated by Maigualida Soler Falcó
Validated date 28/11/2016
observations: