CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0296u

Editorial project management and repair construction element (1 UI)

1,00601,27601,27391,5017,6065,11
Writing project studies and project management for the repair of an item constructive intervention in the first inspection unit, consisting of technical visits for data collection, the current uprising, study and assessment of the deficiencies and detected description of repair construction element, writing project and necessary annexes, writing health and safety study, drafting of study on waste management, direction of the works, coordination of health and safety coordination waste management. Includes visits to work, control and verification of the receipt of products and materials on site, checking the reconsideration and the correct execution of works according to the project, drawing up additional documents, control of construction certificates, emission certificate of work and final drafting of the final document of the state of the works.
%01a%Ancillary costs of labor0,021,10
%02%indirect costs0,031,65
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
RE0265uWriting repair project construction element (1 UI)0,30685,84205,75166,307,95
RE0266uStudy on Safety and Health in repair construction element (1 UI)0,30167,4150,2221,350,90
RE0294uStudy on Waste Management in repair construction element (1 UI)0,30159,0147,7018,950,90
RE0270uProject management in repair construction element (1 UI)0,30368,64110,5969,303,15
RE0269uHealth and Safety Coordination repair construction element (1 UI)0,30246,2173,8637,501,65
RE0295uWaste Management Coordination repair construction element (1 UI)0,30184,6855,4023,101,05
MOU0066hCoordinator / Technician. Professional Level II (Source: IVE). / More information1,0025,0025,0025,001,00
MOU0081hDirector / Technician. Professional Level II (Source: IVE). / More information1,0030,0030,0030,001,00
observations:
It is considered a constructive element constructive elements of each group with similar characteristics that can be treated unitary and homogeneous (eg doors, windows, beams, slabs, etc.). Not included under this heading creeks running costs, if any.
written by Joaquim Iborra Posadas
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 18/03/2018
zone València
observations: Partides relacionades: RE0265, RE0266, RE0267, RE0268, RE0269, RE0270, RE0294, RE0295 i RE0296.
..........
Validated by
profile
Validated date
observations:
Edit price