REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0183u

Health and Safety Coordination house facade renovation

1,00189,74189,7484,165,6644,36
Work relating to Health and Safety Coordination according to the Health and Safety Study prepared for the works described in the implementation plan for the rehabilitation of a building facade house, in accordance with the provisions Royal Decree 1627/97 of 24 October, the Ministry of the Presidency.
%01a%Ancillary costs of labor0,021,15
%02%indirect costs0,034,43
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
RE0188uFurther work health and safety coordinator (distance <20 km)1,0036,6636,6626,662,66
MOU0068hspecialist1,0025,0025,0025,001,00
MOU0066hTechnical coordinator1,0012,5012,5012,501,00
MOU0081hTechnical director1,0020,0020,0020,001,00
REU0763uAverage cost of premiums for professional liability insurance, per 1,000 currency units or technical fees fraction.1,0050,0050,00
REU0762uAverage cost of fees and contributions to the management and visa proceedings in a professional for every 1,000 currency units or technical fees fraction.1,0040,0040,00
written by Joaquim Iborra Posadas
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 10/10/2016
zone València
observations:
..........
Validated by Maigualida Soler Falcó
Validated date 01/02/2017
observations: