CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0172u

Drafting building rehabilitation project (20 IU)

1,003.108,873.108,872.671,07269,9885,92
Writing implementation plan for a building with 20 units or local inspection, consisting of drafting and assessment of the supplementary report from the building, study and assessment of the coves executed (if any) and the approach work aimed at repairing the pathologies detected in structure, roofing, façades and facilities. Includes shift a maximum distance of 20 km, the expert visit for inspection of the property, the report document specification, budget and plans (with an intensity of inspection least 20 IU).
%01a%Ancillary costs of labor0,025,43
%02%indirect costs0,0315,95
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
RE0153uDisplacement of a technician (distance intervals of 10 km or fraction)2,007,8315,666,660,66
RE0414uWriting supplementary report building IEC (20 IU)1,001.021,341.021,34946,43103,20
RE0278uDedication of a technician in the current uprising6,3630,98197,00187,5925,44
RE0174uDedication of a technical report writing7,8335,70279,56266,2531,32
RE0175uDedication of a technical specification writing4,1827,30114,10108,6712,54
RE0176uDedication of a technical drafting budget7,3635,70262,71250,2029,44
RE0177uDedication of a technical drawing of a graphic section8,3634,13285,29271,6633,44
RE0272uStaff time managing administrative proceedings0,508,404,204,000,50
RE0275uDedication of a technical application of regulations1,0042,0042,0040,004,00
RE0276uDedication of technical expertise and the calculation of a structure3,18105,00333,84317,9412,72
MOU0066hTechnical coordinator8,3612,50104,49104,498,36
MOU0081hTechnical director8,3620,00167,18167,188,36
REU0763uAverage cost of premiums for professional liability insurance, per 1,000 currency units or technical fees fraction.2,8350,00141,37
REU0762uAverage cost of fees and contributions to the management and visa proceedings in a professional for every 1,000 currency units or technical fees fraction.2,9740,00118,75
observations:
Not included under this heading the cost of coves and laboratory tests needed to write this project. It is considered independent inspection unit each of the following: every home regardless of the surface; premises for commercial use, warehouse, garage or any other use other than housing on the same level and up to 200 m² of floor area or fraction. It is considered integral rehabilitation works aimed at activities designed to achieve structural and functional adequacy of the building.
written by Joaquim Iborra Posadas
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 7/11/2016
zone València
observations:
..........
Validated by Maigualida Soler Falcó
Validated date 28/11/2016
observations:
edit prices