CODEUDESCRIPTIONQUANTITYPRICE (€)Amount (€)IMPACT OF LABOR (€)MANPOWER (H)IMPACT OF LABOR (%)
RE0170u

Writing supplementary report IEC Building (1 UI)

1,00950,54950,54894,6842,5094,12
Writing supplementary report Building (IEC) of the first inspection unit, which collects the information of the building written and graphic in order to detect, identify and qualify the damages (fissures, cracks, humidities. ..) in building materials, structural and those other symptoms that may indicate damage to the structure, such as the facade, roofs, partitions, joinery and finishes. Includes travel and visit of the technical inspection of the structure of additional properties, sufficiently detailed to obtain necessary parameters for evaluating structural drafting a plan coves of the study results and the estimating the damage index and Corrosion Risk (CI) and the Structural index (EI) and the writing of the supplementary report, based on the Guidelines for the Inspection and Evaluation complementary structures of buildings hormigón existing document recognized DRB Decree 132/2006 05/09 Council.
%01a%Ancillary costs of labor0,0213,71
%02%indirect costs0,0320,57
%Estimating the degree of difficulty or uncertainty (normal 1.00)1,00
MOU0063hTechnical. Professional level III (Source: IVE). / More information12,0022,00264,00264,0012,00
MOU0064hTechnical Assistant / Draftsman higher. Professional level V (Source: IVE). / More information8,0020,58164,64164,648,00
MOU0065hDraftsman. Professional level VII (Source: IVE). / More information8,0018,36146,88146,888,00
MOU0066hCoordinator / Technician. Professional Level II (Source: IVE). / More information2,0025,0050,0050,002,00
MOU0081hDirector / Technician. Professional Level II (Source: IVE). / More information2,0030,0060,0060,002,00
RE0178uData acquisition and leverage current state (1 UI)1,00207,64207,64187,169,50
RE0159uRecognition of an ocular inspection unit building or premises1,0023,1023,1022,001,00
observations:
Not included under this heading the cost of coves and laboratory tests needed to write this report. The intensity of inspection is subject to minimum considered the ease and access permission from the owners. It is considered independent inspection unit each of the following: every home regardless of the surface; premises for commercial use, warehouse, garage or any other use other than housing on the same level and up to 125 m² of floor area or fraction. Adopted the criteria established by the Guidelines and Preliminary Inspection of concrete structures in existing buildings DRB 6/4 of the Valencian Institute of Building.
written by Joaquim Iborra Posadas
company: REHABI-LI-TAR. Gestió i promoció de la rehabilitació SLU
update 9/05/2018
zone València
observations: Partides relacionades: RE0170, RE0413, RE0414, RE0415. Aquesta partida inclou la RE0159, en concepte de reconeixement ocular o inspecció de l'estat de conservació i aquesta mateixa RE0159 també es troba inclosa en la descomposició de la RE0178, en concepte de reconeixement i presa de dades per a l'estat actual; no hi ha, per tant, duplicació de la partida.
..........