Building Project Update - February 28, 2017

posted Feb 28, 2017, 9:48 AM by Christina Maryland   [ updated Feb 28, 2017, 9:48 AM ]
We are currently in the Designer Selection Process.

OPM prepared Request for Services (RFS) – eight (8) firms applied
OPM evaluates and reference checks applicants – sends to MSBA

Three members from the Town sit on the Designer Selection Committee at MSBA:
  • Dr. Peter Sanchioni, Superintendent
  • Dr. Anna Nolin, Assistant Superintendent
  • John Ciccarello

Designer Panel convenes at MSBA and narrows applicants to three. At this meeting, a decision can be made to select an architect. If not a second meeting will be established to interview a short list of firms.

Anticipated Timeline:
  • Submit Information to MSBA Designer Selection Panel (DSP) - 2/24/17
  • MSBA DSP Meeting - 3/14/17
  • MSBA DSP Interview (if decided) - 4/11/17
  • Negotiate Contract with Highest Ranked Firm - 4/14/17
  • Design Kickoff Meeting 4/24/17
Next milestone – Site Selection