CONSTRUCTION UPDATES
Construction Update | 5/14/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 5/17/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 6:50-8:20 AM and 12:40-2:10 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list work is ongoing at the new building.
| Material deliveries will continue along Mill Street and Lucier Drive. |
Gym Wing | Roofing, Framing, MEP Rough in, Masonry, Curtainwall, Drywall, Siding, Painting, locker bases
| Workers within the construction zone.
|
Sitework | Drainage, Water, Sewer, Site Electrical work.
Turf/Road/Sidewalk Subbase
| Large equipment and workers within the construction zone.
Large equipment used to compact the subbase material to the required percentage. |
Construction Update | 5/5/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 5/10/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 6:50-8:20 AM and 12:40-2:10 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list work is ongoing at the new building.
| Material deliveries will continue along Mill Street and Lucier Drive. |
Gym Wing | Roofing, Framing, MEP Rough in, Masonry, Curtainwall, Drywall, Siding, Painting
| Workers within the construction zone.
|
Sitework | Drainage, Water, and Sewer work.
Hauling fill material off site.
Turf/Road/Sidewalk Subbase
| Large equipment and workers within the construction zone.
Large trucks coming in and out of the site
Large equipment used to compact the subbase material to the required percentage.
|
NOTE: Binder paving will be ongoing on Saturday, 5/15, from 8:00 AM to 4:00 PM.
Construction Update | 4/29/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 5/3/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 6:50-8:20 AM and 12:40-2:10 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list work is ongoing at the new building.
| Material deliveries will continue along Mill Street and Lucier Drive. |
Gym Wing | Roofing, Framing, MEP Rough in, Masonry, Curtainwall, Drywall, Siding
| Workers within the construction zone.
|
Sitework | Drainage, Water, and Sewer work.
Hauling fill material off site.
Turf/Road/Sidewalk Subbase
| Large equipment and workers within the construction zone.
Large trucks coming in and out of the site
Large equipment used to compact the subbase material to the required percentage.
|
NOTE: There will be trucks hauling material offsite this Saturday, 5/1, from 8:00 AM to 4:00 PM.
Construction Update | 4/20/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 4/26/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 6:50-8:20 AM and 12:40-2:10 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list work is ongoing at the new building.
| Material deliveries will continue along Mill Street and Lucier Drive. |
Gym Wing | Roofing, Framing, MEP Rough in, Masonry, Curtainwall, Drywall, Siding
| Workers within the construction zone.
|
Sitework | Drainage, Water, and Sewer work.
Hauling fill material off site. | Large equipment and workers within the construction zone.
Large trucks coming in and out of the site |
Construction Update | 4/14/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 4/19/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates will not be closed over April break.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
|
Construction at New KMS
| Punch list work is ongoing at the new building.
| Material deliveries will continue along Mill Street and Lucier Drive. |
Gym Wing | Roofing, Framing, MEP Rough in, Masonry, Curtainwall
| Workers within the construction zone.
|
Sitework | Drainage, Water, and Sewer work.
Storm Trap install and backfill. | Large equipment and workers within the construction zone.
Large equipment and workers near the rear of the future parent drop off loop.
|
Solar | Steel Canopy install in the teacher parking lot. | The three teacher parking lots will be closed to school staff and contractors while Ameresco installs the steel canopy required for the parking lot solar panels.
|
Construction Update | 4/7/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 4/5/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list work is ongoing at the new building.
Loading dock platform and ramp. | Material deliveries will continue along Mill Street and Lucier Drive.
Trucks and workers close to the loading dock area of the new building. This will create some noise and vibrations but is adjacent to the boiler room and kitchen, not the classrooms. Any work that ties into the new building will be done after 1 PM dismissal.
|
Gym Wing | Fireproofing, roofing, framing, curtainwall blocking, MEP Rough in
Set Rooftop Equipment
Fireproofing in Lobby area.
| Workers within the construction zone.
Large truck delivering RTU. Crane on site to place the Unit.
Workers in the enclosed portion of zone 3 lobby. |
Sitework | Drainage, Water, and Sewer work.
Storm Trap install and backfill. | Large equipment and workers within the construction zone.
Large equipment and workers near the rear of the future parent drop off loop. |
Construction Update | 4/2/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 4/5/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list work is ongoing at the new building.
Loading dock platform and ramp. | Material deliveries will continue along Mill Street and Lucier Drive.
Trucks and workers close to the loading dock area of the new building. This will create some noise and vibrations but is adjacent to the boiler room and kitchen, not the classrooms. Any work that ties into the new building will be done after 1 PM dismissal.
|
Gym Wing | Fireproofing, roofing, framing, curtainwall blocking, MEP Rough in
Set Rooftop Equipment
Fireproofing in Lobby area.
| Workers within the construction zone.
Large truck delivering RTU. Crane on site to place the Unit.
Workers in the enclosed portion of zone 3 lobby. |
Sitework | Drainage, Water, and Sewer work.
Storm Trap install and backfill. | Large equipment and workers within the construction zone.
Large equipment and workers near the rear of the future parent drop off loop. |
Construction Update | 3/24/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 3/29/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list work is ongoing at the new building.
Loading dock platform and ramp. | Material deliveries will continue along Mill Street and Lucier Drive.
Trucks and workers close to the loading dock area of the new building. This will create some noise and vibrations but is adjacent to the boiler room and kitchen, not the classrooms. Any work that ties into the new building will be done after 1 PM dismissal.
|
Gym Wing | Fireproofing, roofing, framing, curtainwall blocking, MEP Rough in
Fireproofing in Lobby area.
| Workers within the construction zone.
Workers in the enclosed portion of zone 3 lobby. |
Sitework | Drainage, Water, and Sewer work.
Storm Trap install and backfill. | Large equipment and workers within the construction zone.
Large equipment and workers near the rear of the future parent drop off loop. |
Construction Update | 3/18/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 3/22/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list work is ongoing at the new building.
Loading dock platform and ramp. | Material deliveries will continue along Mill Street and Lucier Drive.
Trucks and workers close to the loading dock area of the new building. This will create some noise and vibrations but is adjacent to the boiler room and kitchen, not the classrooms. Any work that ties into the new building will be done after 1 PM dismissal.
|
Gym Wing | Roof blocking, roof drains, roofing, framing.
Electrical Rough in, drywall, fireproofing.
| Workers within the construction zone.
Workers in the enclosed portion of zone 3 lobby. |
Sitework | Drainage Structures and Piping
Storm Trap Footing | Large equipment and workers within the construction zone.
Large equipment and workers are the rear of the future parent drop off loop. |
Construction Update | 3/12/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 3/15/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list work is ongoing at the new building.
Loading dock platform and ramp. | Material deliveries will continue along Mill Street and Lucier Drive.
Trucks and workers close to the loading dock area of the new building. This will create some noise and vibrations but is adjacent to the boiler room and kitchen, not the classrooms. Any work that ties into the new building will be done after 1 PM dismissal.
|
Gym Wing | Structural Steel detailing.
Slab on Grade Pour
Electrical Rough in, drywall, fireproofing.
| The crane, material, and workers will be within the construction gate. Steel deliveries will be made outside of gate closure times.
Concrete trucks coming into the site via Mill and Lucier.
Workers in the enclosed portion or zone 3. |
Sitework | Drainage Structures and Piping | Large equipment and workers within the construction zone. |
Construction Update | 3/4/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 3/8/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list work is ongoing at the new building.
Loading dock retaining wall. | Material deliveries will continue along Mill Street and Lucier Drive.
Trucks and workers close to the loading dock area of the new building. This will create some noise and vibrations but is adjacent to the boiler room and kitchen, not the classrooms. Any work that ties into the new building will be done after 1 PM dismissal.
|
Gym Wing | Structural Steel detailing.
Electrical Rough in, drywall, fireproofing.
| The crane, material, and workers will be within the construction gate. Steel deliveries will be made outside of gate closure times.
Workers in the enclosed portion or zone 3. |
Sitework | Drainage Structures and Piping | Large equipment and workers within the construction zone. |
Construction Update | 2/25/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 3/1/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list work is ongoing at the new building.
Loading dock retaining wall. | Material deliveries will continue along Mill Street and Lucier Drive.
Trucks and workers close to the loading dock area of the new building. This will create some noise and vibrations but is adjacent to the boiler room and kitchen, not the classrooms. Any work that ties into the new building will be done after 1 PM dismissal.
|
Gym Wing | Structural Steel Erection.
Electrical Rough in.
| The crane, material, and workers will be within the construction gate. Steel deliveries will be made outside of gate closure times.
Workers in the enclosed portion or zone 3. |
Construction Update | 2/17/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 2/22/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list and signage work is ongoing at the new building.
Loading dock retaining wall. | Material deliveries will continue along Mill Street and Lucier Drive.
Trucks and workers close to the loading dock area of the new building. This will create some noise and vibrations but is adjacent to the boiler room and kitchen, not the classrooms. Any work that ties into the new building will be done after 1 PM dismissal.
|
Existing KMS | Clearing debris from the demolition.
| There will be trucks entering the construction zone to be loaded with debris from the demolition and removed.
|
Gym Wing | Continuing foundation excavation and backfill for the new gym wing.
Continue to pour foundations.
Electrical Rough in.
| Trucks and equipment on site behind the new school next to the existing KMS.
Concrete trucks entering the site via Lucier.
Workers in the enclosed portion or zone 3. |
Construction Update | 2/12/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 2/15/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates will not be closed next week due to February Break.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
|
Construction at New KMS
| Punch list and signage work is ongoing at the new building. | Material deliveries will continue along Mill Street and Lucier Drive.
|
Existing KMS | Clearing debris from the demolition.
| There will be trucks entering the construction zone to be loaded with debris from the demolition and removed.
|
Gym Wing | Continuing foundation excavation and backfill for the new gym wing.
Continue to pour foundations.
Electrical Rough in.
| Trucks and equipment on site behind the new school next to the existing KMS.
Concrete trucks entering the site via Lucier.
Workers in the enclosed portion or zone 3. |
Construction Update | 2/8/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 2/8/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list and signage work is ongoing at the new building. | Material deliveries will continue along Mill Street and Lucier Drive.
|
Existing KMS | Abatement on the North side of the existing KMS.
Demolition progressing from the South side to the North side of the existing KMS.
| Large trucks entering and exiting the site.
There will be trucks entering the construction zone to be loaded with debris from the demolition and removed. The trucks will not operate during gate closure times. The demolition will be loud at times. The fire department will be on site spraying the building with water to mitigate dust.
|
Gym Wing | Continuing foundation excavation and backfill for the new gym wing.
Begin to pour foundations.
Electrical Rough in.
| Trucks and equipment on site behind the new school next to the existing KMS.
Concrete trucks entering the site via Lucier.
Workers in the enclosed portion or zone 3. |
Construction Update | 2/1/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 2/1/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list and signage work is ongoing at the new building. | Material deliveries will continue along Mill Street and Lucier Drive.
|
Existing KMS | Abatement on the North side of the existing KMS.
Demolition progressing from the South side to the North side of the existing KMS.
| Large trucks entering and exiting the site.
There will be trucks entering the construction zone to be loaded with debris from the demolition and removed. The trucks will not operate during gate closure times. The demolition will be loud at times. The fire department will be on site spraying the building with water to mitigate dust.
|
Site Work | Continuing foundation excavation for the new gym wing.
| Trucks and equipment on site behind the new school next to the existing KMS.
|
Construction Update | 1/25/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 1/25/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list and signage work is ongoing at the new building. | Material deliveries will continue along Mill Street and Lucier Drive.
|
Existing KMS | Abatement on the North side of the existing KMS.
Demolition progressing from the South side to the North side of the existing KMS.
| Large trucks entering and exiting the site.
There will be trucks entering the construction zone to be loaded with debris from the demolition and removed. The trucks will not operate during gate closure times. The demolition will be loud at times. The fire department will be on site spraying the building with water to mitigate dust.
|
Site Work | Begin foundation excavation for the new gym wing.
| Trucks and equipment on site behind the new school next to the existing KMS.
|
Construction Update | 1/18/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 1/18/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list and signage work is ongoing at the new building. | Material deliveries will continue along Mill Street and Lucier Drive.
|
Existing KMS | Abatement on the North side of the existing KMS.
Demolition on the South side of the existing KMS.
| Large trucks entering and exiting the site.
There will be trucks entering the construction zone to be loaded with debri from the demolition and removed. The trucks will not operate during gate closure times. The demolition will be loud at times. The fire department will be on site spraying the building with water to mitigate dust. |
Site Work | Exploratory test pit adjacent to the existing KMS
| Trucks and equipment on site behind the new school next to the existing KMS. |
Construction Update | 1/11/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 1/11/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule. |
Construction at New KMS
| Punch list and signage work is ongoing at the new building. This work will be scheduled outside of school hours.
| Material deliveries will continue along Mill Street and Lucier Drive.
|
Modulars | Modulars will be removed Monday, 1/11. | Large Trucks towing the modulars will leave campus between 9 am and 12 pm. |
Existing KMS | Abatement at the existing KMS.
Recycling company for the furniture in the existing building will make their final pick up.
| Large trucks entering and exiting the site. |
Site Work | Exploratory test pit adjacent to the existing KMS
Electrical Disconnect by Eversource.
| Trucks and equipment on site behind the new school next to the existing KMS.
|
Construction Update | 1/4/21
Weekly KMS Construction Update and Impacts to campus/community
Week of: 1/4/21
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
|
Construction
| Exterior and Interior punch list and signage work is ongoing at the new building. This work will be scheduled outside of school hours.
Utility disconnects and abatement set up will begin at the existing KMS. | Material deliveries will continue along Mill Street and Lucier Drive. |
Site Work | Landscaping is ongoing.
Foundations for Solar Canopies in the parking lot area | Large equipment on site.
Workers and Concrete trucks in fenced in portions of the parking lot. |
Construction Update | 12/28/20
Weekly KMS Construction Update and Impacts to campus/community
Week of: 12/28/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
|
Furniture, Fixtures, and Equipment | FF&E punch list items ongoing. | Large trucks delivering FF&E coming in through Mill Street and Lucier Drive. |
Transitioning from the Old to the New KMS
| Moving company moving boxes and misc items from the old to the new KMS
Public Auction Pick Up Monday, 12 – 5 PM
| Large trucks maneuvering around the campus.
Members of the public picking up items they bought from the public auction.
|
Construction
| Exterior punch list and signage work is ongoing. Interior punch list is ongoing. Testing and commissioning are ongoing.
| Material deliveries will continue along Mill Street and Lucier Drive.
|
Site Work | Landscaping is ongoing.
Foundations for Solar Canopies in the parking lot area | Large equipment on site.
Workers and Concrete trucks in fenced in portions of the parking lot. |
Construction Update | 12/21/20
Weekly KMS Construction Update and Impacts to campus/community
Week of: 12/21/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule.
|
Furniture, Fixtures, and Equipment | FF&E punch list items ongoing. | Large trucks delivering FF&E coming in through Mill Street and Lucier Drive. |
Construction
| Exterior punch list and signage work is ongoing. Interior punch list is ongoing. Testing and commissioning are ongoing.
| Material deliveries will continue along Mill Street and Lucier Drive.
|
Site Work | Exterior security cameras, Roadway striping, and Landscaping are ongoing.
Foundations for Solar Canopies in the parking lot area | Large equipment on site.
Workers and Concrete trucks in fenced in portions of the parking lot. |
Construction Update | 12/14/20
Weekly KMS Construction Update and Impacts to campus/community
Week of: 12/14/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule.
|
Furniture, Fixtures, and Equipment | FF&E punch list items ongoing. | Large trucks delivering FF&E coming in through Mill Street and Lucier Drive. |
Construction
| Exterior punch list and signage work is ongoing. Interior punch list is ongoing. Testing and commissioning are ongoing.
| Material deliveries will continue along Mill Street and Lucier Drive.
|
Site Work | Exterior security cameras, Roadway striping, and Landscaping are ongoing. | Large equipment on site. |
Construction Update | 12/7/20
Weekly KMS Construction Update and Impacts to campus/community
Week of: 12/7/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
Early Release from School 12/9/20.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule.
Afternoon gate closures will be 11:00 AM – 1:00 PM.
|
Furniture, Fixtures, and Equipment | FF&E punch list items ongoing. | Large trucks delivering FF&E coming in through Mill Street and Lucier Drive. |
Construction
| Exterior punch list and signage work is ongoing. Interior punch list is ongoing. Testing and commissioning are ongoing.
| Material deliveries will continue along Mill Street and Lucier Drive.
|
Site Work | Exterior security cameras and Landscaping are ongoing. | Large equipment on site. |
Construction Update | 11/23/20
Weekly KMS Construction Update and Impacts to campus/community
Week of: 11/23/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
Early Release from School 11/25/20.
No School 11/26 and 11/27
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule.
Afternoon gate closures will be 11:00 AM – 1:00 PM.
No gate closures will be observed. |
Furniture, Fixtures, and Equipment | FF&E deliveries started 10/19/20 and will continue through November. | Large trucks delivering FF&E coming in through Mill Street and Lucier Drive. |
Construction
| Exterior punch list and signage work is ongoing. Interior finishes including drywall, painting, tile, flooring, ceilings and cabinetry are ongoing. Testing and commissioning are ongoing.
| Material deliveries will continue along Mill Street and Lucier Drive.
|
Site Work | Exterior security cameras and Landscaping are ongoing.
Handrail extension work at the Hartford Street walkway ramp to Brown ES. | Large equipment on site.
Equipment and workers at the walkway working on the handrail. Walkers may need to detour around the area of work.
|
Construction Update | 11/16/20
Weekly KMS Construction Update and Impacts to campus/community
Week of: 11/16/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
Early Release from School 11/18/20.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule.
Afternoon gate closures will be 11:00 AM – 1:00 PM. |
Furniture, Fixtures, and Equipment | FF&E deliveries started 10/19/20 and will continue through November. | Large trucks delivering FF&E coming in through Mill Street and Lucier Drive. |
Construction
| Exterior punch list work is ongoing. Interior finishes including drywall, painting, tile, flooring, ceilings and cabinetry are ongoing. Testing and commissioning are ongoing.
| Material deliveries will continue along Mill Street and Lucier Drive.
|
Site Work | Exterior security cameras and Landscaping are ongoing.
Handrail extension work at the Hartford Street walkway ramp to Brown ES.
Fence reconfiguration.
| Large equipment on site.
Equipment and workers at the walkway working on the handrail. Walkers may need to detour around the area of work.
The site fence will be rearranged to prepare for the next phase of construction.
|
Construction Update | 11/6/20
Weekly KMS Construction Update and Impacts to campus/community
Week of: 11/9/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
No School 11/11/20.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule.
No gate closures will be observed. |
Furniture, Fixtures, and Equipment | FF&E deliveries will started 10/19/20 and will continue through November. | Large trucks delivering FF&E coming in through Mill Street and Lucier Drive. |
Construction
| Exterior punch list work is ongoing. Interior finishes including drywall, painting, tile, flooring, ceilings and cabinetry are ongoing. Testing and commissioning are ongoing.
| Material deliveries will continue along Mill Street and Lucier Drive.
|
Site Work | Exterior security cameras and Landscaping are ongoing.
Handrail extension work at the Hartford Street walkway ramp to Brown ES.
| Large equipment on site.
Equipment and workers at the walkway working on the handrail. Walkers may need to detour around the area of work. |
Construction Update | 10/30/20
Weekly KMS Construction Update and Impacts to campus/community
Week of: 11/2/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
No School 11/3.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule.
No gate closures will be observed. |
Furniture, Fixtures, and Equipment | FF&E deliveries will started 10/19/20 and will continue through November. | Large trucks delivering FF&E coming in through Mill Street and Lucier Drive. |
Construction
| Exterior punch list work is ongoing. Interior finishes including drywall, painting, tile, flooring, ceilings and cabinetry are ongoing. Testing and commissioning are ongoing.
| Material deliveries will continue along Mill Street and Lucier Drive.
|
Site Work | Exterior security cameras and Landscaping are ongoing.
Handrail extension work at the Hartford Street walkway ramp to Brown ES.
| Large equipment on site.
Equipment and workers at the walkway working on the handrail. Walkers may need to detour around the area of work. |
Construction Update | 10/26/20
Weekly KMS Construction Update and Impacts to campus/community
Week of: 10/26/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted for the first day of school based on the school schedule.
|
Furniture, Fixtures, and Equipment | FF&E deliveries will started 10/19/20 and will continue through November. | Large trucks delivering FF&E coming in through Mill Street and Lucier Drive. |
Construction
| Exterior punch list work is ongoing. Interior finishes including drywall, painting, tile, flooring, ceilings and cabinetry are ongoing.
| Material deliveries will continue along Mill Street and Lucier Drive.
|
Site Work | Exterior security cameras and Landscaping are ongoing.
Handrail extension work at the Hartford Street walkway ramp to Brown ES. | Large equipment on site.
Equipment and workers at the walkway working on the handrail. Walkers may need to detour around the area of work. |
Construction Update | 10/12/20
Weekly KMS Construction Update and Impacts to campus
Week of: 10/12/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule. Construction Gates are to be closed daily: 7:30-9:30 AM and 12:30-2:30 PM. No School Monday, 10/12/20. | The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted based on the school schedule.
No gate closures will be observed |
Construction | Exterior punch list work is ongoing. Interior finishes including drywall, painting, tile, flooring and cabinetry are ongoing. | Material deliveries will continue along Mill Street and Lucier Drive. |
Site work | Exterior security cameras, Basketball Court Fencing, and Landscaping are ongoing. | Large equipment on site. |
Construction Update | 9/28/20
Weekly KMS Construction Update and Impacts to campus
Week of: 9/28/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule. Construction Gates are to be closed daily: 7:45-9:30AM and 12:30PM-2:00PM. No School Monday, 9/28/20 | The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will be adjusted based on the school schedule.
No gate closures will be observed |
Construction | Exterior punch list work is ongoing. Interior finishes including drywall, painting, tile, flooring and cabinetry are ongoing. The generator will be delivered on Monday, 9/28/20. | Material deliveries will continue along Mill Street and Lucier Drive. Large truck carrying large equipment on campus. |
Site work | Light poles, basketball court top coat and fence, bike racks, site signage and landscaping is ongoing. | Large equipment on site. |
Construction Update | 9/21/20
Weekly KMS Construction Update and Impacts to campus
Week of: 9/21/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule. Construction Gates are to be closed daily: 7:45-9:30AM and 12:30PM-2:00PM.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours will b adjusted for the first day of school based on the school schedule. |
Construction | Exterior punch list work is ongoing. Interior finishes including drywall, painting, tile, flooring and cabinetry are ongoing. The generator will be delivered next week. | Material deliveries will continue along Mill Street and Lucier Drive. Large truck carrying large equipment on the roads. Delivery will be coordinated to avoid impacting school activities. |
Site work | Light poles, basketball court top coat and fence, bike racks, site signage and landscaping is ongoing. | Large equipment on site.
|
Construction Update | 9/14/20
Weekly KMS Construction Update and Impacts to campus
Week of: 9/14/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule. Construction Gates are to be closed daily: 7:45-9:30AM and 12:30PM-2:00PM. Teaching staff returned to Brown Elementary School and Kennedy Middle School.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours may be adjusted based on the school schedule.
Traffic/pedestrian routes and parking areas will be clearly delineated. |
Construction | Exterior punch list work is ongoing. Interior finishes including drywall, painting, tile, flooring and cabinetry are ongoing. The generator will be delivered next week. | Material deliveries will continue along Mill Street and Lucier Drive. Large truck carrying large equipment on the roads. Delivery will be coordinated to avoid impacting school activities. |
Site work | Light poles, basketball court fence, bike racks, site signage and landscaping is ongoing. | Large equipment on site.
|
Construction Update | 9/7/20
Weekly KMS Construction Update and Impacts to campus
Week of: 9/7/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule. Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM. Teaching staff returned to Brown Elementary School and Kennedy Middle School.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues. These hours may be adjusted based on the school schedule.
Traffic routes and parking areas will be clearly delineated. |
Construction | Exterior punch list work is ongoing. Interior finishes including drywall, painting, tile, flooring and cabinetry are ongoing. | Material deliveries will continue along Mill Street and Lucier Drive. |
Site work | Light poles, basketball court fence, bike racks, site signage and landscaping is ongoing. | Large equipment on site.
|
Construction Update | 8/31/20
Weekly KMS Construction Update and Impacts to campus
Week of: 8/31/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule. Construction Gates are to be closed daily (starting 8/27): 7:45-9:15AM and 1:45-3:15PM. Teaching staff returned to Brown Elementary School and Kennedy Middle School.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily. The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
Traffic routes and parking areas will be clearly delineated. |
Construction | Exterior cladding and sun shades. Interior finishes including drywall; painting; tile and cabinetry are ongoing. | Material deliveries will continue along Mill Street and Lucier Drive. |
Site work | Light poles, raised crosswalks, unit pavers, boardwalks, asphalt binder, basketball court, granite curb, bollards, bike racks, and sidewalk placement ongoing. Mill Street signalization work is ongoing. | Large equipment on site.
Work crews at Mill Street/School Entrance. Police details to be on-site. Use caution or avoid the area as sidewalks will be under construction..
|
Construction Update | 8/25/20
Weekly KMS Construction Update and Impacts to campus
Week of: 8/25/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule. Construction Gates are to be closed daily (starting 8/27): 7:45-9:15AM and 1:45-3:15PM. Teaching staff will return to the Brown Elementary School and Kennedy Middle School on 8/27/20.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily. The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
Traffic routes and parking areas will be clearly delineated. |
Construction | Exterior cladding and sun shades. Interior finishes including drywall; painting; tile and cabinetry are ongoing. | Material deliveries will continue along Mill Street and Lucier Drive. |
Site work | Light poles, raised crosswalks, unit pavers, boardwalks, asphalt binder, basketball court, granite curb, bollards, bike racks, and sidewalk placement ongoing. Mill Street signalization work is ongoing. | Large equipment on site.
Work crews at Mill Street/School Entrance. Police details to be on-site. Use caution or avoid the area as sidewalks will be under construction..
|
Construction Update | 8/17/20
Weekly KMS Construction Update and Impacts to campus
Week of: 8/17/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
The Brown/Kennedy campus is CLOSED to the public for the remainder of the summer.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily. |
Construction | Exterior cladding and sun shades. Interior finishes including drywall; painting; tile and cabinetry are ongoing. | Material deliveries will continue along Mill Street and Lucier Drive. |
Site work | Light poles, raised crosswalks, unit pavers, boardwalks, asphalt binder, basketball court, granite curb, bollards, bike racks, and sidewalk placement ongoing. Mill Street signalization work is ongoing. | Large equipment on site.
Work crews at Mill Street/School Entrance. Police details to be on-site. Use caution or avoid the area as sidewalks will be under construction..
|
Construction Update | 8/10/20
Weekly KMS Construction Update and Impacts to campus
Week of: 8/10/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
The Brown/Kennedy campus is CLOSED to the public for the remainder of the summer.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily. |
Construction | Exterior cladding and sun shades. Interior finishes including drywall; painting; tile and cabinetry are ongoing. | Material deliveries will continue along Mill Street and Lucier Drive. |
Site work | Light poles, raised crosswalks, unit pavers, boardwalks, asphalt binder, basketball court, granite curb, bollards, bike racks, and sidewalk placement ongoing. Mill Street signalization work is ongoing. | Large equipment on site.
Work crews at Mill Street/School Entrance. Police details to be on-site. Use caution or avoid the area as sidewalks will be under construction..
|
Construction Update | 8/3/20
Weekly KMS Construction Update and Impacts to campus
Week of: 8/3/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule. The Brown/Kennedy Campus IS CLOSED to the PUBLIC for the remainder of the summer. | The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily. |
Construction | Exterior cladding and interior finishes including drywall; painting; tile and cabinetry are ongoing. | Material deliveries will continue along Mill Street and Lucier Drive. |
Site work | Light poles, raised crosswalks, unit pavers, boardwalks, asphalt binder, basketball court. granite curb and sidewalk placement ongoing. Mill Street signalization work is ongoing. | Large equipment on site. Work crews at Mill Street/School Entrance. Police details to be on-site. Use caution or avoid the area as sidewalks will be under construction. |
Town Work | None | None |
Construction Update | 7/27/20
Weekly KMS Construction Update and Impacts to campus
Week of: 7/13/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule. The Brown/Kennedy Campus IS CLOSED to the PUBLIC for the remainder of the summer. | The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily. |
Construction | Exterior cladding and interior finishes including drywall; painting; tile and cabinetry are ongoing. | Material deliveries will continue along Mill Street and Lucier Drive. |
Site work | Light poles, raised crosswalks, unit pavers, boardwalks, asphalt binder, basketball court. granite curb and sidewalk placement ongoing. Mill Street signalization work is ongoing. | Large equipment on site. Work crews at Mill Street/School Entrance. Police details to be on-site. Use caution or avoid the area as sidewalks will be under construction. |
Town Work | Tree removal | Large equipment on site at the Brown ES back parking lot and along Hartford Street. |
Construction Update | 7/20/20
Weekly KMS Construction Update and Impacts to campus
Week of: 7/20/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule. The Brown/Kennedy Campus IS CLOSED to the PUBLIC for the remainder of the summer. | The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily. |
Construction | Exterior cladding and interior finishes including drywall; painting; tile and cabinetry are ongoing. | Material deliveries will continue along Mill Street and Lucier Drive. |
Site work | Light poles, raised crosswalks, unit pavers, granite curb and sidewalk placement ongoing. Mill Street signalization work ongoing Drilling test wells in the rear parking lot. | Large equipment on site. Work crews at Mill Street/School Entrance. Police details to be on-site. Use caution or avoid the area as sidewalks will be under construction. Large equipment including a drill rig on site. |
Town Work | Resurfacing Brown Elementary School Playgrounds | Large equipment on site.
|
Construction Update | 7/13/20
Weekly KMS Construction Update and Impacts to campus
Week of: 7/13/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule. The Brown/Kennedy Campus IS CLOSED to the PUBLIC for the remainder of the summer. | The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20, revised 5/18/20, regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily. |
Construction | Exterior cladding and interior finishes including drywall; painting; tile and cabinetry are ongoing. | Material deliveries will continue along Mill Street and Lucier Drive. |
Site work | Granite Curb and Sidewalk placement ongoing. Mill Street signalization work ongoing | Large equipment on site. Work crews at Mill Street/School Entrance. Police details to be on-site. Use caution or avoid the area as sidewalks will be under construction. Large equipment including a drill rig on site. |
Town Work |
Construction Update | 5/29/20
Weekly KMS Construction Update and Impacts to campus
Week of: 6/1/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
As school is closed for the remainder of the year, the Brown/Kennedy Campus will be closed to the public.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20 regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
Access for faculty, staff, and facilities is being coordinated, as needed, with the construction efforts. The number one priority for the construction project is safety for the school & community. Please do not hesitate to report any issues.
|
Construction | Masonry, Framing, MEP, Exterior cladding and interior finishes are ongoing. | Material deliveries will continue along Mill Street and Lucier Drive. |
Site work | Parking and sidewalk preparation ongoing.
Install Light Bases along Lucier Drive
Begin drainage and sidewalk preparation on East side of the new school | Sporadic use of compaction equipment.
Vehicles and workers will be working along Lucier Drive.
Large equipment between the old and new KMS.
|
Construction Update | 5/26/20
Weekly KMS Construction Update and Impacts to campus
Week of: 5/25/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
As school is closed for the remainder of the year, the Brown/Kennedy Campus will be closed to the public.
Site will be Closed for the 5/25/2020 holiday.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20 regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
Access for faculty, staff, and facilities is being coordinated, as needed, with the construction efforts. The number one priority for the construction project is safety for the school & community. Please do not hesitate to report any issues.
|
Construction | Masonry, Framing, MEP, Exterior cladding and interior finishes are ongoing. | Material deliveries will continue along Mill Street and Lucier Drive. |
Site work | Install Light Bases along Lucier Drive
Install Communication Structure and Ductbank
Begin drainage and sidewalk preparation on East side of the new school
Fine Grade Lucier Drive and Brown Parking Lot
| Vehicles and workers will be working along Lucier Drive.
Trench work and large equipment between KMS and Brown ES. Trench work that crossed the roadways or parking lot will be covered with steel plates.
Large equipment between the old and new KMS.
Large equipment on the entrance road to the school. |
Construction Update | 5/8/20
Weekly KMS Construction Update and Impacts to campus
Week of: 5/11/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
As school is closed for the remainder of the year, the Brown/Kennedy Campus will be closed to the public.
Teachers will access both KMS and BES on Monday, May 11, 2020 to pack up belongings from the school year.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20 regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
Access for faculty, staff, and facilities is being coordinated, as needed, with the construction efforts. The number one priority for the construction project is safety for the school & community. Please do not hesitate to report any issues.
Access to both schools will be coordinated with the construction team. |
Construction | Masonry, Framing, MEP, Exterior cladding and interior finishes are ongoing. | Material deliveries will continue along Mill Street and Lucier Drive.
|
Site work | Mill Street Road Widening - Verizon to cut lines over to the new poles, poles to be removed, bituminous base to begin.
Install Light Bases along Lucier Drive
Install Communication Structure and Ductbank
Begin drainage and sidewalk preparation on East side of the new school
| Vehicles and workers will be working along Mill Street.
Vehicles and workers will be working along Lucier Drive.
Trench work and large equipment between KMS and Brown ES. Trench work that crossed the roadways or parking lot will be covered with steel plates.
Large equipment between the old and new KMS.
|
Construction Update | 5/1/20
Weekly KMS Construction Update and Impacts to campus
Week of: 5/4/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
As school is closed for the remainder of the year, the Brown/Kennedy Campus will be closed to the public.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20 regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
Access for faculty, staff, and facilities is being coordinated, as needed, with the construction efforts. The number one priority for the construction project is safety for the school & community. Please do not hesitate to report any issues. |
Construction
| Masonry, Framing, MEP, Exterior cladding and interior finishes are ongoing.
Roof Top Unit Delivery | Material deliveries will continue along Mill Street and Lucier Drive.
Large delivery truck and crane on campus. |
Site work | Mill Street Road Widening - Verizon to cut lines over to the new poles, poles to be removed, bituminous base to begin.
Install Light Bases along Lucier Drive
Install Communication Structure and Ductbank
| Vehicles and workers will be working along Mill Street.
Vehicles and workers will be working along Lucier Drive.
Trench work and large equipment between KMS and Brown ES. Trench work that crossed the roadways or parking lot will be covered with stell plates.
|
Construction Update | 4/24/20
Weekly KMS Construction Update and Impacts to campus
Week of: 4/27/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
As school is closed for the remainder of the year, the Brown/Kennedy Campus will be closed to the public.
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20 regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
Access for faculty, staff, and facilities is being coordinated, as needed, with the construction efforts. The number one priority for the construction project is safety for the school & community. Please do not hesitate to report any issues. |
Construction
| Masonry, Framing, MEP, Exterior cladding and interior finishes are ongoing.
Steel Column Erection | Material deliveries will continue along Mill Street and Lucier Drive.
Large equipment on campus. |
Site work | Mill Street Road Widening - Verizon to cut lines over to the new poles, poles to be removed, bituminous base to begin.
Install Light Bases along Lucier Drive
Install Communication Structure and Ductbank
| Vehicles and workers will be working along Mill Street.
Vehicles and workers will be working along Lucier Drive.
Trench work and large equipment between KMS and Brown ES. Trench work that crossed the roadways or parking lot will be covered with stell plates.
|
Construction Update | 4/20/20
Weekly KMS Construction Update and Impacts to campus
Week of: 4/20/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates will be open full-time during the work day due to school closures. The Closed Gate periods will be reinstated once school is back in session.
Parking
| The construction project implemented updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20 regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
Vehicular and pedestrian traffic in the area should continue to use caution.
The number one priority for the construction project is safety for the School & Community. Please do not hesitate to report any issues.
Access to the construction site areas is restricted to authorized and approved personnel only.
Workers will be using the Brown Elementary front parking lots until school is back in session. |
Construction
| Masonry, Framing, MEP, Exterior cladding and interior finishes are ongoing.
Site work is expected to resume in early April | Material deliveries will continue along Mill Street and Lucier Drive.
Large scale trucking operations will be one of the first activities and will be coordinated accordingly with campus conditions. |
Construction Update | 3/30/20
Weekly KMS Construction Update and Impacts to campus
Week of: 3/30/20
Category | Update | Impact |
Construction Site Work Restrictions | Public Construction deemed an essential service by the State of MA on 3/23/20. Construction activity on the project will continue on its normal schedule.
Construction Gates will be open full-time during the work day due to school closures. The Closed Gate periods will be reinstated once school is back in session.
Parking
| The construction project is implementing updated Health & Safety Plans and Policies in accordance with the State of MA’s Guidance Letter issued 3/25/20 regarding COVID-19 Guidelines and Procedures for all Construction Sites and Workers at all Public Work. Compliance monitoring is in effect and is ongoing daily.
Vehicular and pedestrian traffic in the area should continue to use caution.
The number one priority for the construction project is safety for the School & Community. Please do not hesitate to report any issues.
Access to the construction site areas is restricted to authorized and approved personnel only.
Workers will be using the Brown Elementary front parking lots until school is back in session. |
Construction
| Masonry, Framing, MEP, Exterior cladding and interior finishes are ongoing.
Site work is expected to resume in early April | Material deliveries will continue along Mill Street and Lucier Drive.
Large scale trucking operations will be one of the first activities and will be coordinated accordingly with campus conditions. |
Construction Update | 3/21/20
Weekly KMS Construction Update and Impacts to campus
Week of: 3/23/20
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates will be open for the work day: *The closed gate periods will be reinstated once school is back in session.
Parking
Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
Workers may use the school lots for parking until school is back in session. |
Construction
| Masonry, Framing, MEP, and finishes are ongoing.
Work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Guardrail installation at Hartford sidewalk ramp to continue.
| Material deliveries will continue along Lucier Drive. NO deliveries are allowed during drop-off or pick-up times when school is in session. ***Occasionally, the delivery efforts might need to access the work using the temp. KMS road and KMS parking lot. These efforts will be coordinated with KMS and escorted accordingly***.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Work will be coordinated to avoid arrival and dismissal times. |
Construction Update | 2/28/20
Weekly KMS Construction Update and Impacts to campus
Week of: 3/2/20
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:30-8:45AM and 1:45-3:15PM.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Masonry, Framing, MEP, and finishes are ongoing.
Work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Guardrail installation at Hartford sidewalk ramp to continue.
| Material deliveries will continue along Lucier Drive. NO deliveries are allowed during drop-off or pick-up times. ***Occasionally, the delivery efforts might need to access the work using the temp. KMS road and KMS parking lot. These efforts will be coordinated with KMS and escorted accordingly***.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Work will be coordinated to avoid arrival and dismissal times. |
DPW | Drainage investigation work around and behind Barnesdale Road | Truck and equipment around the KMS parking lot and along a portion of Barnesdale Road. |
Construction Update | 2/14/20
Weekly KMS Construction Update and Impacts to campus
Week of: 2/17/20
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:30-8:45AM and 1:45-3:15PM.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Masonry, Roofing, Framing, and MEP work to continue.
Work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Guardrail installation at Hartford sidewalk ramp to continue.
| Material deliveries will continue along Lucier Drive. NO deliveries are allowed during drop-off or pick-up times. ***Occasionally, the delivery efforts might need to access the work using the temp. KMS road and KMS parking lot. These efforts will be coordinated with KMS and escorted accordingly***.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Work will be coordinated to avoid arrival and dismissal times.
|
Construction Update | 1/31/20
Weekly KMS Construction Update and Impacts to campus
Week of: 2/3/20
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:30-8:45AM and 1:45-3:15PM.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Masonry, Roofing, Framing, and MEP work to continue.
Work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Guardrail installation at Hartford sidewalk ramp to continue.
| Material deliveries will continue along Lucier Drive. NO deliveries are allowed during drop-off or pick-up times. ***Occasionally, the delivery efforts might need to access the work using the temp. KMS road and KMS parking lot. These efforts will be coordinated with KMS and escorted accordingly***.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Work will be coordinated to avoid arrival and dismissal times.
|
Construction Update | 1/17/20
Weekly KMS Construction Update and Impacts to campus
Week of: 1/20/20
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Masonry, Roofing, Framing, and MEP work to continue.
Work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Guardrail installation at Hartford sidewalk ramp to continue.
| Material deliveries will continue along Lucier Drive. NO deliveries are allowed during drop-off or pick-up times. ***Occasionally, the delivery efforts might need to access the work using the temp. KMS road and KMS parking lot. These efforts will be coordinated with KMS and escorted accordingly***.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Work will be coordinated to avoid arrival and dismissal times.
|
Construction Update | 1/10/20
Weekly KMS Construction Update and Impacts to campus
Week of: 1/13/20
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Masonry, Roofing, Framing, and MEP work to continue.
Work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Guardrail installation at Hartford sidewalk ramp to continue.
| Material deliveries will continue along Lucier Drive. NO deliveries are allowed during drop-off or pick-up times. ***Occasionally, the delivery efforts might need to access the work using the temp. KMS road and KMS parking lot. These efforts will be coordinated with KMS and escorted accordingly***.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Work will be coordinated to avoid arrival and dismissal times.
|
Construction Update | 12/20/19
Weekly KMS Construction Update and Impacts to campus
Week of: 12/23/19
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Structural Steel, Masonry, Roofing, Framing, and MEP work to continue.
Work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Guardrail installation at Hartford sidewalk ramp to continue. | Material deliveries will continue along Lucier Drive. NO deliveries are allowed during drop-off or pick-up times. ***Occasionally, the delivery efforts might need to access the work using the temp. KMS road and KMS parking lot. These efforts will be coordinated with KMS and escorted accordingly***.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Work will be coordinated to avoid arrival and dismissal times.
|
***Concrete floor placements***: Monday 12/23/19 Note: Schedule may change due to weather.
| *** Efforts will be made to avoid arrival and dismissal times as much as possible. However, the main construction gate could be open during drop-off and pick-up times and concrete trucks could be in school traffic flow. Please use caution.
*** Efforts will be made to reduce the duration of the concrete floor finishing in order to mitigate disturbances to the surrounding community. At this time, work is not anticipated to extend beyond normal construction hours (7 pm). However, if conditions change, the project team will provide as much advance notice as possible.*** |
Construction Update | 12/13/19
Weekly KMS Construction Update and Impacts to campus
Week of: 12/16/19
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Structural Steel, Masonry, Roofing, Framing, and MEP work to continue.
Work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Guardrail installation at Hartford sidewalk ramp to continue. | Material deliveries will continue along Lucier Drive. NO deliveries are allowed during drop-off or pick-up times. ***Occasionally, the delivery efforts might need to access the work using the temp. KMS road and KMS parking lot. These efforts will be coordinated with KMS and escorted accordingly***.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Work will be coordinated to avoid arrival and dismissal times.
|
***Concrete floor placements***: Monday 12/16/19, Wednesday 12/18/19 Note: Schedule may change due to weather.
| *** Efforts will be made to avoid arrival and dismissal times as much as possible. However, the main construction gate could be open during drop-off and pick-up times and concrete trucks could be in school traffic flow. Please use caution.
*** Efforts will be made to reduce the duration of the concrete floor finishing in order to mitigate disturbances to the surrounding community. At this time, work is not anticipated to extend beyond normal construction hours (7 pm). However, if conditions change, the project team will provide as much advance notice as possible.***
|
Construction Update | 12/6/19
Weekly KMS Construction Update and Impacts to campus
Week of: 12/9/19
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Structural Steel, Masonry, Roofing, Framing, and MEP work to continue.
Work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Guardrail installation at Hartford sidewalk ramp to continue. | Material deliveries will continue along Lucier Drive. NO deliveries are allowed during drop-off or pick-up times. ***Occasionally, the delivery efforts might need to access the work using the temp. KMS road and KMS parking lot. These efforts will be coordinated with KMS and escorted accordingly***.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Work will be coordinated to avoid arrival and dismissal times.
|
***Concrete floor placements***: Monday 12/9/19, Tuesday 12/10/19 Note: Schedule may change due to weather.
| *** Efforts will be made to avoid arrival and dismissal times as much as possible. However, the main construction gate could be open during drop-off and pick-up times and concrete trucks could be in school traffic flow. Please use caution.
*** Efforts will be made to reduce the duration of the concrete floor finishing in order to mitigate disturbances to the surrounding community. At this time, work is not anticipated to extend beyond normal construction hours (7 pm). However, if conditions change, the project team will provide as much advance notice as possible.***
|
Construction Update | 11/27/19
Weekly KMS Construction Update and Impacts to campus
Week of: 12/2/19
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Structural Steel, Masonry, Roofing, Framing, and MEP work to continue.
Structural Steel work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Guardrail installation at Hartford sidewalk ramp to continue.
Install bollards around electrical equipment along temp road.
| Material deliveries will continue along Lucier Drive. NO deliveries are allowed during drop-off or pick-up times. ***Occasionally, the delivery efforts might need to access the work using the temp. KMS road and KMS parking lot. These efforts will be coordinated with KMS and escorted accordingly***.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Work will be coordinated to avoid arrival and dismissal times.
Crews might need to set up temporarily along the temp road. Work will be coordinated to avoid arrival and dismissal times.
|
***Concrete floor placements***: Tuesday 12/3 Note: Schedule may change due to weather.
| *** Efforts will be made to avoid arrival and dismissal times as much as possible. However, the main construction gate could be open during drop-off and pick-up times and concrete trucks could be in school traffic flow. Please use caution.
*** Efforts will be made to reduce the duration of the concrete floor finishing in order to mitigate disturbances to the surrounding community. At this time, work is not anticipated to extend beyond normal construction hours (7 pm). However, if conditions change, the project team will provide as much advance notice as possible.***
|
Construction Update | 11/22/19
Weekly KMS Construction Update and Impacts to campus
Week of: 11/25/19
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Structural Steel, Masonry, Roofing, Framing, and MEP work to continue.
Structural Steel work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Guardrail installation at Hartford sidewalk ramp to continue.
| Material deliveries will continue along Lucier Drive. NO deliveries are allowed during drop-off or pick-up times. ***Occasionally, the delivery efforts might need to access the work using the temp. KMS road and KMS parking lot. These efforts will be coordinated with KMS and escorted accordingly***.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Work will be coordinated to avoid arrival and dismissal times.
|
***Concrete floor placements***: Tuesday 11/26 Note: Schedule may change due to weather.
| *** Efforts will be made to avoid arrival and dismissal times as much as possible. However, the main construction gate could be open during drop-off and pick-up times and concrete trucks could be in school traffic flow. Please use caution.
*** Efforts will be made to reduce the duration of the concrete floor finishing in order to mitigate disturbances to the surrounding community. At this time, work is not anticipated to extend beyond normal construction hours (7 pm). However, if conditions change, the project team will provide as much advance notice as possible.*** |
Construction Update | 11/15/19
Weekly KMS Construction Update and Impacts to campus
Week of: 11/18/19
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Structural Steel, Masonry, Roofing, Framing, and MEP work to continue.
Structural Steel work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Guardrail installation at Hartford sidewalk ramp to continue.
| Material deliveries will continue along Lucier Drive. NO deliveries are allowed during drop-off or pick-up times. ***Occasionally, the delivery efforts might need to access the work using the temp. KMS road and KMS parking lot. These efforts will be coordinated with KMS and escorted accordingly***.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Work will be coordinated to avoid arrival and dismissal times.
|
***Concrete floor placements***: Tuesday 11/19 Note: Schedule may change due to weather.
| *** Efforts will be made to avoid arrival and dismissal times as much as possible. However, the main construction gate could be open during drop-off and pick-up times and concrete trucks could be in school traffic flow. Please use caution.
*** Efforts will be made to reduce the duration of the concrete floor finishing in order to mitigate disturbances to the surrounding community. At this time, work is not anticipated to extend beyond normal construction hours (7 pm). However, if conditions change, the project team will provide as much advance notice as possible.***
|
Construction Update | 11/8/19
Weekly KMS Construction Update and Impacts to campus
Week of: 11/11/19
PLEASE NOTE ALL ITEMS IN RED
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM. *No gate closure requirements on 11/11/19 as there is no school.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Structural Steel work to continue.
Structural Steel work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Site light installation at “new” Jean Burke Drive.
Guardrail installation at Hartford sidewalk ramp to continue.
Masonry Veneer
| Steel deliveries will continue along Lucier Drive. NO Deliveries are allowed during drop-off or pick-up times.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Potential need to relocate some BES staff vehicles for short periods of time.
Work will be coordinated to avoid arrival and dismissal times.
Masonry deliveries along Lucier Drive to continue the through the Fall. NO Deliveries are allowed during drop-off or pick-up times.
|
***Concrete floor placements***: Tuesday 11/12 Wednesday 11/13 Note: Schedule may change due to weather.
| *** Efforts will be made to avoid arrival and dismissal times as much as possible. However, the main construction gate could be open during drop-off and pick-up times and concrete trucks could be in school traffic flow. Please use caution.
*** Efforts will be made to reduce the duration of the concrete floor finishing in order to mitigate disturbances to the surrounding community*** |
Construction Update | 11/7/19
Construction Update | 11/1/19
Weekly KMS Construction Update and Impacts to campus
Week of: 11/4/19
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Structural Steel work to continue.
Structural Steel work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Site light installation at “new” Jean Burke Drive. | Steel deliveries along Lucier Drive started 9/10 and will continue the through the Fall. NO Deliveries are allowed during drop-off or pick-up times.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Potential need to relocate some BES staff vehicles for short periods of time.
|
***Concrete floor placements***: Monday 11/4 Friday 11/8
Guardrail installation at Hartford sidewalk ramp to continue. | *** Efforts will be made to avoid arrival and dismissal times as much as possible. However, the main construction gate could be open during drop-off and pick-up times and concrete trucks could be in school traffic flow. Please use caution.
Work will be coordinated to avoid arrival and dismissal times. |
Construction Update | 10/25/19
Weekly KMS Construction Update and Impacts to campus
Week of: 10/28/19
Category
Update
Impact
Construction Site Work Restrictions
Construction Gates are to be closed daily:
7:45-9:15AM and 1:45-3:15PM.
All workers are to park within the fencing.
Workers have all been CORI’D but should not be interacting with parents or students.
The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
Construction
Structural Steel work to continue.
Structural Steel work at new Auditorium space (closest to temp road/Brown Elementary) to continue.
Site light installation at KMS temporary parking lot.
Steel deliveries along Lucier Drive started 9/10 and will continue the through the Fall.
NO Deliveries are allowed during drop-off or pick-up times.
Crews might need to access the work by moving man lifts along the temp. road. Work will be coordinated to avoid drop-off and pick-up times.
Potential need to relocate some staff vehicles for short periods of time.
Structural Steel “Topping Off” Ceremony 10/29/19 at 11AM.
Minimal visitor parking at Brown front lot.
Construction Update | 10/18/19
Weekly KMS Construction Update and Impacts to campus
Week of: 10/21/19
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
|
Construction
| Structural Steel work to continue.
| Steel deliveries along Lucier Drive started 9/10 and will continue the through the Fall. NO Deliveries are allowed during drop-off or pick-up times.
|
Punchlist work for Summer 2019 work will continue. Railing at new sidewalk from Hartford Street will be installed.
Installation of Steel Bollards around electrical transformers along temporary road to KMS. | Workers and equipment could be on campus throughout the day. All workers are CORI’ed and work will not take place during drop-off or pick-up times. Periods of single lane travel might occur after AM drop-off and before PM pick-up. |
Construction Update | 10/11/19
Weekly KMS Construction Update and Impacts to campus
Week of: 10/14/19
Category | Update | Impact |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM.
NO SCHOOL: 10/14 - Columbus Day
Early Release: 10/16
Concrete slab pours will occur all day on: Tuesday: 10/15 Friday: 10/18
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
GATE CLOSURE TIMES WILL NOT BE IN PLACE.
GATE CLOSURE TIMES WILL BE ADJUSTED ACCORDINGLY.
Finishing of concrete slabs could extend into evening/nighttime hours (i.e after 5:00 PM) on these days and will produce some noise from the site. Natick PD will be aware.
|
Construction
Construction
| Structural Steel work to continue.
Concrete slab pours scheduled for all day on: Tuesday: 10/15 Friday: 10/18
| Steel deliveries along Lucier Drive started 9/10 and will continue the through the Fall. NO Deliveries are allowed during drop-off or pick-up times.
Police Details have been ordered to help with concrete truck deliveries. Efforts will be made to mitigate impacts to Closed Gate periods as much as possible.
|
Construction | Punch list work for Summer 2019 work (i.e landscape; hardscape around BES) to continue. Workers and equipment could be on campus throughout the day.
Installation of Steel Bollards around electrical transformers along temporary road to KMS. | All workers are CORI’ed and work will not take place during drop-off or pick-up times.
Periods of single lane travel might occur after AM drop-off and before PM pick-up. |
Construction Update | 10/4/19
Weekly KMS Construction Update and Impacts on campus
Week of: 10/07/19
Category | Update | Impact |
Campus Circulation | New Traffic patterns are effective as of 8/28/19. DRIVE SLOWLY! USE TURN SIGNALS! Please obey stop signs.
| Allow a few extra minutes for pick-up and drop-off routines. |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM.
NO SCHOOL 10/9: Yom Kippur
Concrete slab pours will occur all day on: Monday: 10/7 Wednesday: 10/9 Friday: 10/11
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with parents or students.
| The number one priority for the construction project is safety for the School Community. Please do not hesitate to report any issues.
GATE CLOSURE TIMES WILL NOT BE IN PLACE.
Finishing of concrete slabs will extend into the evening/nighttime hours (i.e after 7:30 PM) these days and will produce some noise from the site. Natick PD will be aware.
|
Construction
Construction
| Structural Steelwork to continue.
Concrete slab pours scheduled for all day on: Monday: 10/7 Wednesday: 10/9 Friday: 10/11
| Steel deliveries along Lucier Drive started 9/10 and will continue through the Fall. NO Deliveries are allowed during drop-off or pick-up times.
Police Details have been ordered to help with concrete truck deliveries. Efforts will be made to mitigate impacts to Closed Gate periods as much as possible. |
Construction | Punchlist work for Summer 2019 work (i.e landscape; hardscape around BES) to continue. Workers and equipment could be on campus throughout the day.
Installation of Steel Bollards around electrical transformers along the temporary road to KMS. | All workers are CORI’ed and work will not take place during drop-off or pick-up times.
Periods of single-lane travel might occur after AM drop-off and before PM pick-up. |
Construction Update | 9/20/19
Weekly KMS Construction Update and Impacts on campus
Week of: 9/23/19
Category | Update | Impact |
Campus Circulation | New Traffic patterns effective as of 8/28/19. DRIVE SLOWLY! USE TURN SIGNALS! Please obey stop signs.
| Allow a few extra minutes for pick-up and drop-off routines. |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM.
EARLY RELEASE DAY 9/25: GATE CLOSURE TIMES WILL BE ADJUSTED ACCORDINGLY.
All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with Parents or Students.
| The number one priority for the construction project is Safety for the School Community.
Please do not hesitate to report any issues. |
Construction | Structural Steel work to continue. | Steel deliveries along Lucier Drive started 9/10 and will continue the through the Fall. NO Deliveries are allowed during drop-off or pick-up times.
|
Construction | Punchlist work for Summer 2019 work (i.e landscape; hardscape around BES) to continue. Workers and equipment could be on campus throughout the day. | All workers are CORI’ed and work will not take place during drop-off or pick-up times. |
Construction Update | 9/13/19
Weekly KMS Construction Update and Impacts on campus
Week of: 9/16/19
Category | Update | Impact |
Campus Circulation | New Traffic patterns are effective as of 8/28/19. DRIVE SLOWLY! USE TURN SIGNALS! Please obey stop signs.
| Allow a few extra minutes for pick-up and drop-off routines. |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM. All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with Parents or Students. | The number one priority for the construction project is Safety for the School Community. Please do not hesitate to report any issues. |
Construction | Structural Steelwork to continue. | Steel deliveries along Lucier Drive started 9/10 and will continue through the Fall. NO Deliveries are allowed during drop-off or pick-up times.
|
Construction | Punchlist work for Summer 2019 work (i.e landscape; hardscape around BES) to commence. Workers and equipment could be on campus throughout the day. | All workers are CORI’ed and work will not take place during drop-off or pick-up times. |
Construction Update | 8/30/19
KMS Construction Project
Weekly Update and Impacts
Week of: 9/2/19
(Construction Site Closed on 9/2 for Labor Day)
Category | Update | Impact |
Campus Circulation | New Traffic patterns are effective as of 8/28/19. DRIVE SLOWLY! USE TURN SIGNALS! Drivers exiting KMS please note: Cross-traffic (from BES and/or Lucier Dr.) along “NEW” Jean Burke Drive does not have to stop. Please obey the STOP sign and use caution when turning onto “New” Jean Burke drive when leaving KMS.
| Allow a few extra minutes for pick-up and drop-off routines. |
Construction Site Work Restrictions | Construction Gates are to be closed daily: 7:45-9:15AM and 1:45-3:15PM. All workers are to park within the fencing. Workers have all been CORI’D but should not be interacting with Parents or Students. | The number one priority for the construction project is Safety for the School Community. Please do not hesitate to report any issues. |
Construction | Foundation work for the new building to be completed. Prep for steel erection will be ongoing Underground plumbing and electrical work will be ongoing within the new building footprint. | Daily deliveries of material along Lucier Drive. NO Deliveries are allowed during drop-off or pick-up times. |
Construction | Steel erection to commence. | Crane to be set-up within construction site 9/5 and 9/6. Steel deliveries will begin along Lucier Drive starting 9/9 through the Fall. NO Deliveries are allowed during drop-off or pick-up times.
|
Construction Update | 8/9/19
BROWN/KENNEDY CAMPUS IS CLOSED TO THE PUBLIC UNTIL 8/19
As we approach the start of the school year, we want to prepare parents on the changes to the morning routines as it relates to navigating the Brown/KMS campus.
A large part of the drop off/pick up process will be adjusting to the normal "new school" procedures; however, keep in mind that this is also a live construction site and we need to account for it in our morning routines.
Navigating the campus:
A guidance video is forthcoming. Stay tuned!
- Plan to add 20 minutes to morning routines until you become familiar with the new layout of the campus.
- Walking paths will be open. (Read below for site updates about the paths).
Please see the reader accessible PDF or image of the site map for pedestrian access points and navigation. - Drivers MUST FOLLOW DIRECTIONS from adults directing traffic on campus.
- Read ALL signs.
- Maintain LOW SPEEDS at all times.
- Please do not use drop off time to check out the campus.
- If possible, avoid driving to campus to avoid the anticipated congestion.
Site Updates:
- Barnsdale walking path will be open as before.
- Old Surrey walking path is restored and will be open.
- New pedestrian walking path on campus (a navigation video is forthcoming)
- Medical/Health Info drop off
8/26; regular building hours
A few things to note:
- The campus is an active (live) construction site.
- The construction site is enclosed with fencing and locks; therefore, there is a low probability of anyone "wandering" into the space.
Construction Update | 8/2/19
BROWN/KENNEDY CAMPUS IS CLOSED TO THE PUBLIC UNTIL 8/19
KMS Construction Project
Update and Impacts
Week of: 8/5/19
Category
Update
Impact
Construction
Foundation work for the new building continues
Construction of temporary parking lot and access roads.Daily truck deliveries of concrete and gravel along Lucier and Jean Burke Drive
Fence Reconfiguration/ Roadway
Traffic pattern and gate times to Brown and KMS.
Brown staff to use new road to/from front lot. KMS to use the same route. Gates for both schools will be open 6 am - 3:30 pm.
Utilities
Eversource to pull primary power to switching station and then to KMS/Brown ES.
Power shut down in both schools. Power cut over date TBD (Pending Eversource).
Utilities
Poles along Lucier Drive to be removed once Eversource pulls primary power.
Large equipment and workers on Lucier Drive. One lane of travel.
Tree Cutting
Dead trees along Lucier Drive will be removed.
Large equipment and workers on Lucier Drive. One lane of travel.
Site work
Prep and Install site improvements along Brown ES.
Large concrete / gravel trucks and more workers in close proximity to Brown ES.
New Entrance at KMS
Complete interior finishes.
Workers will continue to create the new main entrance at the back of KMS. Loud tools being used. Dust will be controlled as much as possible
Modulars
Modular fit out.
Modulars are set and work will continue to tie the services into KMS.
Construction Update | 7/29/19
BROWN/KENNEDY CAMPUS IS CLOSED TO THE PUBLIC UNTIL 8/19
KMS Construction Project
Update and Impacts
Week of: 7/29/19
Category
Update
Impact
Construction
Foundation work for the new building continues
Construction of temporary parking lot and access roads.Daily truck deliveries of concrete and gravel along Lucier and Jean Burke Drive
Fence Reconfiguration/ Roadway
Traffic pattern and gate times to Brown and KMS.
Brown staff to use new road to/from front lot. KMS to use the same route. Gates for both schools will be open 6 am - 3:30 pm.
Utilities
New Water service install will continue next week.
Water will be shut off to KMS on 7/29/19.
Utilities
Install New Gas Service
One lane of travel along Lucier Drive.
Tree Cutting
Dead trees along Lucier Drive will be removed.
Large equipment and workers on Lucier Drive.
Mill Street
Traffic signal conduit and pull boxes. Relocated catch basins. Install curb and roadway.
The traffic pattern may be disrupted at Mill Street.
Site work
Prep and Install site improvements along Brown ES.
Large concrete / gravel trucks and more workers in close proximity to Brown ES.
New Entrance at KMS
Interior framing and door frame install. Glass Install. Exterior stair and ramp install. Removal of interior partition.
Workers will continue to create the new main entrance at the back of KMS. Loud tools being used. Dust will be controlled as much as possible
Modulars
Modular fit out.
Modulars are set and work will continue to tie the services into KMS.
Construction Update | 7/2/19
BROWN/KENNEDY CAMPUS IS CLOSED TO THE PUBLIC UNTIL 8/19
After walking the construction site on July 1st, construction employees have indicated that residents are walking dogs and throwing blue (and other colors) poop bags into the catch basins around the property.
Below is a picture of just one of the catch basins, which are now being emptied and cleaned. (The blue in center are the doggy poop bags)
We want to remind everyone to take their poop bags off campus and dispose of them properly.
Construction Update | 6/26/19
KMS Construction Project
Weekly Update and Impacts
Week of: 7/1/19
Category | Update | Impact |
Construction | Foundation work for the new building continues | Daily truck deliveries of concrete and gravel along Lucier and Jean Burke Drive |
Utilities | Underground electric and Tel-Com duct bank work will continue along Lucier Drive | One lane of travel along Lucier Drive. |
Utilities | New Water service install will continue next week. | May be periods of temporary water shut offs in all or part of the schools. Summer staff will be notified prior to this occuring. |
Fencing / traffic reroute | Fencing will be adjusted next week after binder paving is complete this week. | Once the fencing is moved, Brown ES staff will use the New Jean Burke Drive to access their parking lot. KMS will continue to use the Southern road and enter through the loading dock. |
Tree Cutting | Dead trees along Lucier Drive will be removed. | Large equipment and workers on Lucier Drive. |
Site Demo | Demolition at Mill Street and Lucier Drive will continue. | The traffic pattern may be disrupted at Lucier Drive and Mill Street. |
Demolition | Demolition for the enabling work for the new entrance will continue next week. | Several workers in the building. Loud tools being used. Dust will be controlled as much as possible. Debris being taken out of the building in dumpster carts. Isolated shut downs of electrical and fire alarm to be coordinated with the school staff and FD. |
New Entrance | Framing new openings at the new main entry will begin. | Workers will be starting the new work to create the new main entrance at the back of KMS. Loud tools being used. Dust will be controlled as much as possible |
Salvage | Removing and storing Mosiac panels at the old front entry will begin. | Construction workers close to the front entrance working on dismantling and storing the mosiac panels. Loud tools being used. Dust will be controlled as much as possible |
Modulars | Modulars will be delivered next week. | Modulars will be set and then work will begin to tie into KMS. |
Signage | Install of temporary signage and striping will begin. | Road signage and striping may not be in place at the beginning of the week. |
Site Closure | Site will be closed for July 4 holiday |
|
Construction Update | CAMPUS CLOSED | 6/24/19
Public Access:
Dog walkers; joggers; bicyclists; etc. are asked to not use the campus roads and trails until further notice.
Site Security:
While the site is secure, many site elements are in temporary states that change daily and could be hazardous to public pedestrian or vehicular traffic.
Construction Update 6/21/19
KMS Construction Project
Weekly Update and Impacts
Complementary Documents:
Category | Update | Impact |
Construction | Foundation work for the new building continues | Daily truck deliveries of concrete and gravel along Lucier and Jean Burke Drive |
Utilities | The underground electric ductbank will begin along Lucier Drive | One lane of travel along at Lucier Drive when tree work is going on. |
Utilities | Gas shut off for KMS | Gas to KMS will be shut off but an electric heater was installed to provide hot water for the school summer staff. |
Paving | Jean burke drive is no longer paved. | As least one lane of traffic will be open but the road is not paved. |
Tree Cutting | The dead trees along Lucier Drive will be removed. | Equipment and workers on Lucier Drive. |
Site Lighting | Site lighting will be tied into KMS | An electrician will be in KMS. |
Site Demo | Demolition at Mill Street and Lucier Drive will begin. | The traffic pattern may be disrupted at Lucier Drive and Mill Street. |
Demolition | Demolition for the enabling work for the new entrance will begin on Monday. | Several workers in the building. Loud tools being used. Dust will be controlled as much as possible. Debris being taken out of the building in dumpster carts. |
Modulars | Modulars will be delivered 6/26. | Modulars will be set and then work will begin to tie into KMS. |
Construction Update 6/14/19
KMS Construction Project
Update and Impacts for Week of 6/17/19
Category | Update | Impact |
Construction | Foundation work for the new building continues; construction of temporary parking lot and access roads continues behind the existing KMS.
| Loud site work equipment; daily truck delivery of gravel and concrete along Lucier and Jean Burke Drive.
|
Fencing | Install fencing for Summer work (6/19-8/19) around the KMS front parking lot
| Access to KMS from the front parking lot will be CLOSED starting 6/20. After 6/20 school access is from rear or loading dock entrance.
|
Fencing | Install fencing along Brown ES path to HARTFORD starting 6/20.
| Public access (pedestrian) from HARTFORD will be CLOSED from 6/20 – 8/19. Access to Brown from Barnesdale path.
|
Fencing | Install fencing at LUCIER DRIVE
| Public access (pedestrian AND vehicular) from MILL St will be CLOSED from 6/20-8/19. Authorized school personnel only.
|
Tree Cutting | Crews to cut remaining trees in the landscaped islands in the front lawn/parking lot areas of KMS and along LUCIER Drive starting 6/19. | Some teacher parking spots will be displaced from near the trees. ONE-LANE of travel along LUCIER when tree work is on-going.
|
Utility work | Install of a new pole at LUCIER drive for tel/data services to be installed. | Temporary ONE-LANE of traffic along LUCIER during install. |
Construction Update 6/7/19
See below for the timeline of activities happening on the Kennedy and Brown campuses over the summer. Attached is an annotated map with notes of the areas on campus that will experience impacts and the anticipated dates for those activities.
A good rule of thumb is that campus and buildings will not be accessible by the public from the end of the school year June 19, 2019 through August 19, 2019.
Exception: Administrators, custodians and administrative assistants will be the only authorized personnel on both campuses. These individuals will be able to be in the building and conduct their work save for the exceptions noted below.
June - August 2019
Do not expect access to the schools (including classrooms) and roads, unless you work at the school in the summer as an administrator, assistant, or custodian.
After Students Leave School (14th)
Fencing will be moved around, parking may be impacted but staff can still enter and exit until June 19.
June 17th
Expect delays due to one-lane travel on the Brown/KMS campus at all times
Fencing installation along roadway on to dual campus and on Brown access road
Modular install begins--footings prep
Technology Staff move items out of current IT office so it can be remodeled for use as front door supervisor’s office (affects staff only)
June 19th
No access to campuses from Hartford Street
No access to campuses from Mill Street
Access to Brown only from Barnesdale and will not flow through the campuses reliably
Surrey Lane access will be blocked, remade, realigned and restored around July 1 (estimation)
Custodians at Brown need to clean and prep modulars prior to July 1
June 20th
There will be no access to the side parking lot at Brown. Construction vehicles only. (staff should no longer visit campus)
Front of old KMS will no longer be accessible.
No access to the old KMS parking lot.
One lane traffic on campus, expect delays
Deliveries will be routed to the new front entrance which is now the back entrance.
June 24th
A new access road will be used to enter campuses
Expect one-lane access on campus
No public access to Mill Street
Improvements to Lucier Drive will begin
Mosaic on front door will be removed and preserved for future installation
Modular classrooms delivered to site (2)
Complete install temporary water heater
Hot water access will be available after this for whole summer until cut over of utilities in late July/early August.
1st/2nd Week of July
Water switch over
No staff access at all, including summer workers --principals, assistants, custodians (dates TBD) (affects school staff only and their ability to work in schools; if working this week during power outages, move to town hall for admins and assistants, to NHS for custodians)
This could be a 1-2 day cut over
July 15-16th (exact dates within these weeks may fluctuate)
Eversource collaboration, various changeovers. (affects school staff only and their ability to work in schools; if working this week during power outages, move to town hall for admins and assistants, to NHS for custodians)
School Technology Staff will need to reboot and check technology after the power outages and check phone services
End of July/Beginning of August
Possible power disruption to Brown and KMS (affects school staff only)
Fire alarm cut over (this date is not yet firm but no staff can be in building without a working alarm)
District technology to arrange to test video surveillance system
August 7th
Paving the permanent parking lot at Brown
August 19th
Summer phase of construction to be completed
New access road to campus will be operational.
Weeks Prior to School
A video and map of new roads and drop-off procedures / circulation routes will be sent to the community at large for the 2019-2020 School Year.
In addition, you can view an aerial site map for a visual of the areas on campus where there will be impacts or work will be completed on the various dates outlined above.
Please know that we are in the process of determining the following:
If there was a time capsule placed in the old KMS and where it is (no one can yet answer this, even Dr. Keefe!)
A time capsule committee led by Sandy Lemon has been convened to create a NEW capsule to be placed in the new KMS building
Plants around the campus are subject to conservation expectations for the construction team. The team is expected to preserve, relocate and reuse whatever they can. We cannot, therefore, allow the public in to dig up plants. In addition, from June 19 on, there is no access to the closed campus at all.
Arrangements are being made, like those made for the old NHS, to have a “say goodbye to old KMS” event that would allow for final visits and to distribute both memorabilia and aspects of the building that cannot be sold or salvaged for reuse.
This is an overview memo, but we will update you all summer through our usual means:
KMS Project Site: bit.ly/kmslatest
Twitter: www.twitter.com/kmsprojectnps
Emails: http://bit.ly/kmspjemails
Construction will be ongoing, and we know that you will have concerns to share or questions to ask along the way.
We want to encourage you to connect with us anytime by contacting the building committee via email, kmsbuildingcommittee@natickps.org.
All messages sent here go to everyone on the building committee and will receive a response. In addition, you can call my office 508-647-6500 to share your feedback.
Construction Update 5/31/19
Construction Update 5/21/19
- Taking down the basketball hoop and the climbing cube structure.
- Setting up new fence and jersey barriers that cut out a portion of our playgroup.
- Removing the black fence that is between the playground and the modulars.
- Extending the fence line by the path so that it adds the grassy area to the playground.
- Setting up a portable basketball hoop in the black top area.
Construction Update 5/20/19
As a part of the tree removal process, the construction team will be creating a new Surrey Path. This is part of the planned creation of emergency egress from Surrey to the future athletic field that is part of the project.
Construction Update 5/10/19
- Gravel subbase for the temporary road.
- Strip topsoil at the rear parking area and begin trucking out.
- Zone 1 area building layout and excavation.
- Rebar delivery and installation.
- Install temporary power to the trailers.
- Install new Eversource primary pole
Construction Update 5/3/19
Zone 1 building layout and excavation. Rebar delivery and installation. Commence layout for the underground duct bank work.
Install temporary power to the trailers.
Construction Update 4/26/19
Construction Update 4/18/19
- Tree clearing.
- Topsoil removal within fencing.
- Survey and Layout for Foundations.
- Setting up the constructions site work trailers.
- Construction material deliveries to fenced in areas.
Groundbreaking 3/27/19
Construction Update - 2019
PRE-CONSTRUCTION UPDATES
Building Design Process | Presentation Posted (August 29, 2018)
New Documents Posted in Minutes and Agendas (Dec 18, 2017)
[FORUM UPDATE] 10/10 Community Forum Live Video Broadcast Available for Viewing (Oct 17, 2017)
[PROJECT UPDATE] Ballot Question Approved for March 27, 2018 Town Election (Oct 17, 2017)
New Documents Posted in Document Library (Sept 26, 2017)
[FORUM UPDATES] New items posted and Video Recap (July 13, 2017)
Additionally, the meeting was recorded on Facebook Live and can be viewed here: https://www.facebook.com/natickps/videos/1586662588032997/.
[UPCOMING] Second Community Forum on July 12 @ 7pm (June 30, 2017)
Kennedy Middle School Building Project
Community Forum
Wednesday, July 12, 2017
7:00 PM to 8:30 PM
Kennedy Middle School, Auditorium
This is the second public forum—in a series of forums—that will focus on helping the community understand feasibility options for the proposed building project. The full forum schedule is (tentatively) listed as:
- Wednesday, May 31, 2017: LISTENING: Gathering community input
- Wednesday, July 12, 2017: ALTERNATIVES: Understanding the feasibility options [UPCOMING]
- TBD, September 2017: RECOMMENDED SOLUTION: Understanding the proposed solution
The KMSBC will consider the broadest range of options and possibilities to address the operational and educational constraints of the John F. Kennedy Middle School. This forum and the subsequent forums play a vital role in that process. Please attend and share your thoughts, ideas, and suggestions. The focus of each workshop is different so citizens are encouraged to attend all. The workshops will build on each other.
Your feedback and input are important. We hope you are able to attend this forum. We look forward to working cooperatively with the Natick community on this great opportunity to develop a solution for upgrading Kennedy and ensuring our educational objectives are met, while also addressing much-needed building systems and infrastructure issues.
If you're unable to attend the meeting, you can watch the meeting on Facebook Live by visiting the Natick Public Schools page (www.facebook.com/natickps).
Should you have questions or comments, email the project team: kennedyproject@natickps.org.
[NEW ITEMS POSTED] Document Library (June 7, 2017)
[FORUM UPDATES] Community Forum Follow-up (June 1, 2017)
UPCOMING] First Building Project Community Forum on May 31, 2017
[Project Milestone] Site Selection (May 18, 2017)
Architect Approved by MSBA (March 30, 2017)
Building Project Update (February 28, 2017)
- Dr. Peter Sanchioni, Superintendent
- Dr. Anna Nolin, Assistant Superintendent
- John Ciccarello
- Submit Information to MSBA Designer Selection Panel (DSP) - 2/24/17
- MSBA DSP Meeting - 3/14/17
- MSBA DSP Interview (if decided) - 4/11/17
- Negotiate Contract with Highest Ranked Firm - 4/14/17
- Design Kickoff Meeting 4/24/17
Timeline Outline: Request for Services for Owner's Project Manager Phase (Sept 30, 2017)
- Thursday, October 13, 2016 – Last date to submit RFS and advertisement to the MSBA for review
- Thursday, November 3, 2016 – Place advertisement in Central Register and local newspaper
- Wednesday, November 9, 2016 – Ad appears in Central Register and newspaper
- Wednesday, November 23, 2016 – Applications due to the District
- Wednesday, December 14, 2016 – Complete selection package due to the MSBA for review
- Monday January 9, 2017 – OPM Review Panel Meeting
Owner's Project Manager (OPM) Selected (December 20, 2016)
School Committee Motion (April 25, 2016)
The Advisory Nominating Committee shall collect by Friday, May 6, 2016, the names of nominees to the Kennedy Middle School Building Committee proposed by other appointing authorities as defined in the statutes and regulations of the Massachusetts School Building Authority.
The Advisory Nominating Committee shall review the credentials of persons who have expressed to the School Committee interest in serving on the Kennedy Middle School Building Committee. The committee may contact such persons for further information in order to possess equivalent knowledge and information about all interested persons.
The Advisory nominating Committee shall propose to the School Committee on Monday, May 23, 2016, a motion for the following purposes:
to constitute the Kennedy Middle School Building Committee,
to appoint nominees to the Kennedy Middle School Building Committee, including the nominees specified by other appointing authorities and a slate of nominees for appointment under the authority of the School Committee, to provide such other constitutional or procedural rules and guidelines as the Advisory Nominating Committee may deem useful in promoting effective operation of the Kennedy Middle School Building Committee and consistent with the rules and guidelines of the Massachusetts School Building Authority governing school building committees, and to set a first meeting date for the Kennedy Middle School Building Committee.