Welcome to the project site for Natick's Kennedy Middle School building project.

This site is dedicated to informing the Natick community-at-large about the Kennedy Middle School building project by providing timely updates and project-based information.

Latest News

  • Architect Approved by MSBA On March 28, 2017, the MBSA approved Ai3, the first choice, as the architect for the Kennedy Building Project. We are appreciative of the MSBA for their work with us ...
    Posted Apr 3, 2017, 7:25 AM by Christina Maryland
  • Building Project Update - February 28, 2017 We are currently in the Designer Selection Process.OPM prepared Request for Services (RFS) – eight (8) firms appliedOPM evaluates and reference checks applicants – sends to MSBAThree members from ...
    Posted Feb 28, 2017, 9:48 AM by Christina Maryland
Showing posts 1 - 2 of 6. View more »


Current Project Calendar

  • Submit Information to MSBA Designer Selection Panel (DSP) - 2/24/17
  • MSBA DSP Meeting - 3/14/17
  • MSBA DSP Interview (if decided) - 4/11/17
  • Negotiate Contract with Highest Ranked Firm - 4/14/17
  • Design Kickoff Meeting 4/24/17
Next milestone – Site Selection




About Natick Public Schools
Natick Public Schools is a community dedicated to ensuring students achieve high standards in a safe, trusting, respectful environment where learning is exciting, dynamic, and engaging. Our mission is to educate our students by providing high-quality instruction.