Timeline Outline: Request for Services for Owner's Project Manager Phase

posted Sep 30, 2016, 5:35 AM by Christina Maryland   [ updated Sep 30, 2016, 7:43 AM ]
The District will begin the OPM and Designer Selection procurement process. The Massachusetts School Building Authority (MSBA) offered the following dates as an outline that correlate with the January 9, 2017 OPM Review Panel Meeting.

Please note that these dates are not set in stone and may be subject to change.
OPM SELECTION TIMELINE
  • Thursday, October 13, 2016 – Last date to submit RFS and advertisement to the MSBA for review
  • Thursday, November 3, 2016 – Place advertisement in Central Register and local newspaper
  • Wednesday, November 9, 2016 – Ad appears in Central Register and newspaper
  • Wednesday, November 23, 2016 – Applications due to the District
  • Wednesday, December 14, 2016 – Complete selection package due to the MSBA for review
  • Monday January 9, 2017 – OPM Review Panel Meeting