The California K-12 High Speed Network, through the Broadband Infrastructure Improvement Grant (BIIG), has authorized installation of high speed Internet circuits for the sites appearing on this page.  There are two steps that go into the installation of new Internet circuits.  First, telecommunication carriers such as AT&T, Comcast, Verizon and other carriers will install the new Internet circuits. Second, after the circuits are installed Education Networks of America (ENA) Integration Services will install new hardware such as routers to complete the installation process.

The report below will be updated as telecommunication carriers install circuits and equipment is installed at school sites.

Key for Status column:
Engineering: Project is currently being engineered by awarded telecommunication carrier
WIP: Work is in progress, telecommuncation carrier is in process of circuit installation
Hardware: Circuit installation has been completed, installation of hardware is in progress
Completed: Project is complete and circuit is passing data