Announcements

April 5, 2017

posted Apr 5, 2017, 8:43 AM by Roy Rakszawski   [ updated Apr 5, 2017, 8:44 AM ]

Work completed during the past two weeks:
  • Plaster ceiling removal in dishwasher room
  • Transite panel abatement
  • Footings, elevator pit slab & walls, foundation cmu, generator pad
  • Waterproofing membrane below elevator pit slab
  • Mechanical rough-in (duct & heating pipe)
  • Electrical rough-in at Jacques & Magowan (fire alarm, power, lighting)
  • Corridor wall & ceiling fire stop
  • Drywall Magowan corridor ceiling
  • Water heater installation at Magowan
Work planned for the next two weeks:
  • Concrete (Ridgway main office slab, elevator machine room footing, generator pad Magowan, electric room footing & slab)
  • Drywall and fire tape bottom of ceiling joists in Magowan corridor
  • Mechanical rough-in (duct, heating pipe, fire dampers)
  • Electrical rough-in (feeder conduit, fire alarm, power & lighting)
  • Waterproofing installation at elevator pit
  • CMU at Ridgway main office addition and elevator shft
  • VAT & carpet removal
  • Structural steel installation
  • Set mechanical equipment curbs
  • Roof work Jacques & Magowan
  • Fire stopping
  • Install primary feeder conduits

March 22, 2017

posted Mar 22, 2017, 9:43 AM by Roy Rakszawski

The Ridgway main entrance is still closed, but work is progressing on the addition.  Soon, the concrete foundation will be poured.  A lot of work has been completed in the hallway ceilings - wiring, pipes, ductwork have been installed to accommodate the new systems that are coming later.  

February 23, 2017

posted Feb 23, 2017, 10:32 AM by Roy Rakszawski

Construction of a new entrance and conference has begun at Ridgway School.  The main entrance will be closed for approximately 2 weeks.  Visitors should follow the signs to a temporary entrance near the gym.  Click HERE to see pictures of the construction.

February 13, 2017

posted Feb 13, 2017, 5:23 AM by Roy Rakszawski   [ updated Feb 13, 2017, 5:33 AM ]

Magowan ceiling tiles and materials are being removed to make way for electrical and duct work.  In some areas, temporary lighting is in place.   Effective February 14, 2017, the Ridgway School main entrance will be closed for 1 to 2 weeks.  After that, the main entrance will be relocated.  Please follow the signs to the temporary entrance.  

January 24, 2017

posted Jan 24, 2017, 7:06 AM by Roy Rakszawski   [ updated Jan 24, 2017, 7:06 AM ]

The Edgewater Park Township School District will soon begin the next phase of building renovations associated with the Bond Referendum.  Workers will begin removing ceilings in the halls of Magowan School around January 26, 2017.  The work will take place after school hours and on weekends.  You can expect to see some construction vehicles in the neighborhood and hear a limited amount of noise associated with the projects.  We apologize for any inconvenience.  Please don't hesitate to contact my office if you encounter any problems or have any questions. 

Dr. R.

1-5 of 5