Network Infrastructure Upgrades

Description of Network Upgrades 
  • Wiring closets to support new equipment and cabling
  • Faster access to network resources for student/staff computers
  • WIFI access throughout the entire campus
  • IP Telephones in classrooms and offices
Completed Upgrades School Year 2014 - 2015
Coles HS                                 Completed April 2014
Windsor Park ES                     Completed May 2014
Jones ES                                 Completed July 2014
Mireles ES                               Completed September 2014
Dawson ES                              Completed February 2015
Montclair ES                            Completed April 2015

Expected Completion Dates for 2015 - 2016
Mary Grett                               Completion Date September 2015                                   
Barnes ES                               Completion Date October 2015                       
Club Estates ES                      Completion Date January 2016