It was too cold on Friday to do any siding as the vinyl would just crack and break up. The house had been inspected by the Energy consultants and a City framing inspector. There were six volunteers and Alex that showed for work. The work for the day was to correct the structural work that failed the City inspection and plug holes. We relocated two 2x4 studs and installed three new studs to fully support the large microlam beams at all supporting walls. Fire blocking was installed between bottom stair treads and the first floor and the landing floor. 2x6 risers were install over the master bedroom ceiling to raise an attic storage floor above the insulation thickness. Alex had no additional work assignments for us and we broke off around 2:30. It was cold and we mind leaving early! |