| PMP Questions 61 - 80 61. Which of the following is true? 62. Resource leveling will generally: 63. A task was scheduled to use two persons, full time, and take two weeks to complete.Instead, the project manager was only able to assign one person to this task. At the endof two weeks, the person assigned to the task was 75% complete. What is the costperformance index? 64. Five tasks are scheduled to be completed in sequence. Each task has a finish-startrelationship with the next task. Each has one day of total float. As of today, task one andtwo have been completed on schedule. How many days of float remain in the scheduleof these tasks? a. Two 65. Which of the following is considered to be a simulation technique? 66. The main difference between the two types (ADM, arrow diagramming method, and PDM, precedence diagramming method) of the critical path method (CPM) of scheduling is: 67. The project schedule is not used to determine: 68. A project manager wants to make a trip to California by car. The project manager knows how many miles it will be to drive to California, the current price of gasoline, and how many miles the car will go on a gallon of gasoline. From this information he or she can calculate the estimated cost of the gasoline for the trip. This is a form of what kind of estimating technique? 69. A project manager wants to make a trip to California by car. The project manager knows someone who has made this trip before. This person has a similar car to the one that the project manager has, and the person has kept good records on the money spent for fuel on the trip. The distance that the project manager will travel is 10% farther than the other person’s trip. By multiplying the cost of fuel reported by the other person by 1.1, the project manager is performing what kind of estimate? 70. To distinguish top-down estimates from bottom-up estimates, it would be correct to say that the bottom-up estimate would be: 71. A project manager and the project team identify several specific risks in a project. The expected value of these risks is estimated at $10,000. The impact on the project brought about by these risks is estimated at $40,000. What value should be entered into the management reserve for these risks? 72. A project manager and the project team identify several specific risks in a project. The expected value of these risks is estimated at $10,000. The impact on the project brought about by these risks is estimated at $40,000. What value should be entered into the contingency reserve for these risks? 73. What characteristic best describes the cost baseline? 74. A project is formed to produce a product that will be used for transporting people. Costs that are associated with the project that occur after the delivery of the product to the customer are considered to be what kind of cost? 75. A project team receives an approved change request from customer. The team has previously estimated that the cost to implement this change is $10,000. The customer has agreed to pay this amount for the additional work. The customer realizes that there is a 50 percent chance that this change will not work and will later be removed. What change, if any, should be made in the budget? 76. The act of doing anything that will help to bring future project performance into line with the project plan is called: 77. Which of the following choices would be an acceptable cause for “rebaselining” a $10 million project? 78. In terms of earned value reporting, a project is considered complete when: 79. The time-phased cost of the project that reflects the expenditures rather than the consumption of a resource that will be used to measure and monitor cost performance on a project is the: 80. A large piece of equipment is needed for the project. It will be retained and used after the project is completed. The equipment has a value of $500,000, and it has a scrap value of $50,000 at the end of its useful life of ten years. If the sum of the years’ digits method of depreciation is used, what is the depreciation that is taken at the end of the third year?
Answers: 61. C 62. C 63. B 64. B 65. C 66. A 67. D 68. C 69. B 70. C More accurate 71. C 72. A 73. B 74. C 75. C 76. C 77. B 78. D 79. A 80.C |
"PMI", "PMP" "PMBOK" are marks of the Project Management Institute
(PMI)
which are registered in the United States of America and in other nations
PMI has not participated in the creation of this self assessment test and
has not reviewed it for correctness.
This test is for self assessment only and no guarantee is
given for passing the PMP®.
No content from this site can be reproduced without the permission of the owner.