| PMP Questions 41 - 60 41. A project manager is managing a project that has reached the end of planning phase. The work scope has been agreed to and definitive cost estimates have been completed for the project. The total estimated cost of the project is $100,000. It is reasonable to expect that the project will not cost over which of the following value? The following information and questions 42 through 51 refer to Figure 1 A schedule was developed for a project to install windows in an apartment building. The project is a rush job, and the contractor has agreed to schedule the work on a single shift basis but will work seven days per week until the job is done. The project is to begin on May 1. 43. What is the free float for activity F? 44. What is the free float for activity D? 45. What is the critical path of the project? 46. What is the late start for activity F? 47. How long is the project in days? 48. What is the early start for activity F? 49. If there is a delay in activity F of six days, what is the effect on the project completion date? 50. What is the early finish date for activity A? 51. The above diagram is called: 52. If a project manager were to make Thanksgiving dinner, two of the activities that might be of concern would be roasting the turkey and baking the sweet potatoes. In order to ensure that these two items will be finished cooking and will come out of the oven at the same time, what type of relationship should he or she use in the schedule between these two activities? Questions 53 through 56 refer to the diagram in Figure 2 and the table that follows.
53. What is the expected value of the number of days to complete the project? 54. It is desirable to make an estimate that has a greater than 95% chance of being correct. Which of the following ranges of time for the impletion of the project best describes this probability of being correct? a. 33.31 to 31.36 55. What is the expected value of the duration for activity B? 56. What is the standard deviation for the duration of activity B?
58. Crashing the schedule means: 59. The original schedule (for a project, a work package, or an activity). Plus or minus approved changes, is called: 60. Schedules are used in many ways. In a project to build a bridge the project manager wants to use a tool that will show the scheduled activities in such a way that it is easy to see when each activity starts and finishes and which activities are taking place at the same time. Which tool should be used?
Answers: 41.B 42. B 43.B 44. D 45.A 46. C 47. B 48. C 49. B 50. A 51. C 52. A 53. C 54. B 55. B 56. C 57. D 58. A 60. B |
"PMI", "PMP" "PMBOK" are marks of the Project Management Institute
(PMI)
which are registered in the United States of America and in other nations
PMI has not participated in the creation of this self assessment test and
has not reviewed it for correctness.
This test is for self assessment only and no guarantee is
given for passing the PMP®.
No content from this site can be reproduced without the permission of the owner.

