| PMP Questions 161 - 180 161. A project manager discovers that there is a part of the project that contains some risk. His strategy with this risk is to subcontract the work to an outside supplier by using a firm fixed-price contract. Which of the following must the project manger do? 163. A problem occurs in the design of a grocery cart. In this case it is determined that the wheels will wear out much quicker in areas of heavy snow and ice because the salt will corrode the wheel bearings. Using sealed bearing wheels will significantly increase cost, and it is determined that the carts themselves will be rusty and damaged at about the same time the wheel bearings begin to fail. By injecting the wheel bearings with a high temperature grease the life of the wheel bearings is increased considerably. The project recommends using the high temperature grease. This is called: 164. The contingency budget will: 165. A risk has four possible outcomes. Given the following information, what is the expected value of this risk? 166. The project has done its risk analysis. In the process of risk identification the project team has determined that there are risks that will probably happen that have not been identified or evaluated except by noting that other projects of this type have historically had a certain amount of risk discussed in the lessons learned of the project. This project team should set aside money to handle these risks in which financial category? 168. The effect of risk on schedule dates for the project creates an array of dates that are possible for project completion. In a typical project the most likely date for the project will have which of the following relationships with the expected value for the project completion date? 169. A project manager is reviewing the risks of her project. One of the risks she is reviewing has an impact of $25,000 and an associated probability of 10%. The risk is associated with an activity that is the predecessor to seven other activities in the schedule. All eight activities are on the critical path. The seven other activities have a budget of $75,000. What is the expected value of this risk? 170. In probability theory, what is the probability that if you roll two dice (cubes with consecutive numbers 1 to 6 on each of the six faces) you will have at least one 6? 171. A project manager is looking at the risk associated with the project schedule. Realizing that if the risks occur the project will be delivered to the stakeholders late, the project manager decides to consider the risk and promise delivery later than the most likely project completion date. He then takes the time between the promise date and the most likely completion date and distributes it among the activities of the project schedule. This creates float in the schedule. This process is called: 173. A project manager and her project team are analyzing risk in their project. One of the things that they might do to help identify potential risks or opportunities would be to review: 174. A project manager holds the first risk meeting of the project team. The client is present at the meeting. At the meeting several risks are identified and assigned to members of the project team for evaluation and quantification. The result of the meeting is: 175. In the Monte Carlo technique, what is the critically index? 176. The management reserve for the project contains: 177. A project manager uses the breakeven point to justify his project. He presents this as a justification for buying a new machine. What risk does the project manager run by using this technique to justify buying a new machine for his company? 178. Goldratt’s critical chain theory says that in order to reduce risk in schedules we should: 180. A risk event in a project is something that can have an effect on the project:
Answers: 161.C 162. A 163. C 164. B 165. D 166. C 167. A 168. A 169. D 170. B 171. C 172. D 173. C 174. C 175. B 176. C 177. A 178. D 179. C 180. C |
"PMI", "PMP" "PMBOK" are marks of the Project Management Institute
(PMI)
which are registered in the United States of America and in other nations
PMI has not participated in the creation of this self assessment test and
has not reviewed it for correctness.
This test is for self assessment only and no guarantee is
given for passing the PMP®.
No content from this site can be reproduced without the permission of the owner.