Located north of The Placencia Hotel and Residences on the northern end of the Peninsula.  Development plan includes six 5-story buildings, swimming pool, 300 foot pier, office and staff quarters.  Rumors of a casino, but no casino approved by the Belize Department of the Environment (DOE).

The developer is The Placencia Land & Development Co. Ltd.  Environmental Compliance Plan approved by DOE on 23 March 2007.

The developer constructed a large groyne just south of the project for use in loading and unloading materials.  The developer was discovered dredging/mining the beach at the construction site for the development  in August 2008.  When originally discovered, the developer claimed to be complying with sand by-passing orders issued by DOE in connection with a groyne constructed by the developer.

The Belize Land Utilization Authority denied issuing a permit for the groyne and the Belize Department of Geology denied issuing a permit for the dredging.  DOE disclaimed any responsibility for anything at all.

 




 
Copal Beach Groyne and Barge
 Beach Dredging at Copal Beach, Aug. 2008

 Construction at the site continues.





Attachments (4)

  • 1 July 2009.pdf - on Jul 1, 2009 1:18 PM by mtoy@destinationsbelize.com (version 1)
    38k View Download
  • Copal Beach ECP.pdf - on Mar 19, 2009 3:06 PM by mtoy@destinationsbelize.com (version 1)
    860k View Download
  • DOE letter re Copal Beach.JPG - on Mar 19, 2009 3:05 PM by mtoy@destinationsbelize.com (version 1)
    104k View Download
  • Unauthorized Dredging on Placencia Beach, The Reporter, 31 Aug 2008, page 34.jpg - on Apr 4, 2009 12:51 PM by mtoy@destinationsbelize.com (version 1)
    225k View Download