Resurface of Swimming Pool

Please find below the schedule of activities for the Resurfacing of the Swimming Pool.

Scheduled Start Date April 5th, 2005
Scheduled Finish Date May 8th, 2005
Projected Finish Date May 8th, 2005

April 4th - April 15th
Commence Demolition
Remove Coping Stones, all tile, bush hammer swimming pool and prepare surface for plaster.

April 18th - April 23rd
Prepare and level coping bed for new stones. Set stones

April 25th - April 30th
Set tile beds. Install water line, depth marker, racing lane and break tile

May 2nd & 3rd
Acid wash and TSP pool surface and prepare for plaster

May 5th - 7th
Pool Plaster
Fill Pool