Please find below the schedule of activities for the
Resurfacing of the Swimming Pool.
Scheduled Start Date April 5th, 2005
Scheduled Finish Date May 8th, 2005
Projected Finish Date May 8th, 2005
April 4th - April 15th
Commence Demolition
Remove Coping Stones, all tile, bush hammer swimming pool and
prepare surface for plaster.
April 18th - April 23rd
Prepare and level coping bed for new stones.
Set stones
April
25th - April 30th
Set
tile beds. Install
water line, depth marker, racing lane and break tile
May
2nd & 3rd
Acid
wash and TSP pool surface and prepare for plaster
May
5th - 7th
Pool
Plaster
Fill Pool |