Here's some information I received on the timing of the Julian and St. James street conversions from 1 way to two way...
 

The Julian/St. James Couplet Conversion Project will convert Julian St. (between 4th St. and 17th St. ) and St. James St . (between 4th St. and 19th St. ) from one way streets to two way streets.  As part of this conversion project, the 11 traffic signals will be modified with new signal equipment, new drain inlets and ADA compliant ramps, the 19 non-signalized intersections will be upgraded with new drain inlets and ADA compliant ramps, Julian St. will be re-surfaced with new asphalt, and St. James St. will be spot repaired and overlaid with slurry seal.  We’re wrapping up the Plans and Specifications and are planning to advertise the project in July.  The construction is expected to start in November 2009 and complete in the Summer of 2011.

 