The steps required to establish include:
  • Making a decision on the land use mechanism and legal structure - (Done: Rural Landsharing Communities, SEPP 15)
  • Gathering documentation to support Land Use Change DA to Council - (Current)
  • Get pre-lodgement advice from Council's Development Control Unit (Senior Town Planner, Senior Health and Building Surveyor and the Senior Development Engineer)
  • Submitting DA for Land Use Change to council
  • Research most appropriate legal entity - (Current)
  • Creating legal entity
  • Developing ecovillage cultural, environmental and financial framework. (ie How we do things here) - (Current)

Timeframe

Sept 24: Meet to put together info to go to friendly town planner
Sept 29: Meet with friendly town planner
Oct 1: Meet to continue work
Oct 16: Pre-DA meeting with SSC and visit Imago
Oct 22: Meet to continue work
Oct 29: Meet with friendly town planner
Nov 6: Meet to continue work
Nov 13: Pre-DA meeting SSC and visit Imago
Nov 19: Meet to continue work
Nov 26: Meet to continue work
Dec 3: Meet to continue work
Dec 10: Meet to continue work
Dec 14: Submit DA to council