Building work started on our extension on Monday 30th March.Please view the photos below to see progress so far. Click Here to view a copy of the plans. Week 1Day 1 - 30th March - Foundations and soak-away dug.![]() Day 9 - 9th April - Removed render from top floor at front - Installed window lintels and new tray for existing roofWeek 3Day 10 - 14th April - Wall repairs finished and first layer of new rendering applied on kitchen and top floor front walls - Porch started (initialy in the wrong place!) - New roof supports startedDay 11 - 15th April - Porch nearly finished, roofing has been started - Outer layer of rendering applied to upper kitchen wall - First roof trusses in placeDay 12 - 16th April - Top layer of rendering around top floor done - base layer rendering above new section done - new roof trusses and soffit boards complete - two new windows installedDay 13 - 17th April - Rendering complete on top floor - mended rubbish original plumbing - new soffits fitted - new door frame installedWeek 4Days 14-16 - 20th-22nd April - New door fitted - rendering complete - some painting - new windows in original building - walls rearranged in old living room - stone cladding removed form fireplaceDays 17-18 -23rd / 24th April Wall knocked through to extension and RSJs fitted. Roof made weather-tight. Study walls completed and prepared for plastering.Week 5Days 17-21 - 27th April to 1st May. Mostly indoor work now. Plastering study and Sitting room. Knocked door through to kitchen. Roof tiling and porch completed. Floor concrete laid in extended area. utility and shower room stud-work installed. Electrical and plumbing fit. We did some exterior painting!![]() ![]() ![]() ![]() ![]() Week 6Days 22-25 - 5th to 9th
May. Highlights this week - Drainage installed (and existing updated). Utility and shower rooms partitioned, Sitting room plastered and door broken through to kitchen. Coving to sitting room and study.Week 8Days 22-25 - 18th to 22nd May. Decorating!! William and Amanda decorated sitting room and study, and carpet installed at end of week. Furniture returned. Some outside painting and tiling inside. Plumbers and electricians completed final connections. Utility and shower room fitting out completed. Fireplace built. |

































