A New Access Door
New work in the roundhouse to May 8th 2007.
The stall 12 side of the East firewall. X marks the spot for the new door.
The lower section of the ladder has been removed to storage, the door opening outline has been diamond-sawed and work on the lintel has begun.
The opposite side of the wall in what is now a storage room.
The steel lintel is now in place. Note the new brickwork.
Surplus bricks have been removed.
The new opening is a forklift access route into the new space which will contain a tank farm and drive-in beer cooler.
Steel channel sides are welded in place and painted safety yellow.