Architect : Summary of Services : Section IV of TOR Appendices

    

Appendix- A —Description of the Services

 

A.        SCHEDULE OF SERVICES

 

A.1      Summary of the Services

 

A.1.1   The consultant (Gandhara designs) will furnish or provide the following services as detailed in paragraphs B and C here below only if specifically designated in the following table:

 

Design Stage:

Services

Responsibilities

Notes

1. Site survey

Consultant

Gandhara designs to appoint surveyor

2. Perusal of the Client’s brief  AND CONCEPTUAL DESIGNS

TSAO & McKOWN

PRINCIPAL ARCHITECTS

3.Preparation and Presentation of Design Development Drawings

Consultant

GD

4. Making of all Construction working drawings with all detailing as required by the project.

Consultant

GD

5. Preparation of all structural design and drawings required by the project.

Consultant

GD

6. All Electrical Designs and Details

Consultant

GD

7. All Plumbing and Sanitation Drawings and Details

Consultant

GD

8. Bid Documents preparation

Consultant

GD

9. Getting drawings approved by the concerned authorities

Consultant/ client

GD

10. Preparation of Specifications and estimates based on the BSR (Bhutan Schedule of Rates)

Consultant

GD

11. Preparation of bills of quantity and document for tendering for construction.

Consultant

GD

12. Site Development Design and Details

Consultant

GD

13. Interior Designs / Security Systems/HVAC Works (IF ANY)

Client

To be done by Specialised Consultants

14. Assisting the client in the evaluation of submitted bids for construction

Consultant

 

15. Construction Contract Administration

Consultant/ client

Client to appoint project manager

16. On-site representation

Consultant/ client

Client to appoint project manager

17. Construction Management

Consultant

 

18. As-built drawings

Consultant

 

19. Post-construction services

Client

 

20. Defect Liability Period & maintenance services

Consultant

 

21. Issuance of Final completion Certificate

Consultant

 

 

Work Supervision Stage:

 

Co-ordination of different/specialized services done by other consultants

 

Appointing an engineer on site for supervision of works

 

Arranging for Architect to visit site as per requirement

 

Maintaining site record books and providing progress reports to client

 

Ensuring the quality of construction

 

Ensuring that the construction is carried out according to design

 

Acting as link body between client and the contractor

 

Making changes in drawing that are necessary due to unforeseen circumstances

 

Providing all additional detailing if required during construction

 

Making measurement of work

 

Verification and passing of running bills put up by the contractor

 

Declaring the construction work complete and handing over

 

To maintain the critical path method charts during the progress of the project construction and submit progress report to the client from time to time.

 

Any discrepancies with the contractor related to design/ specification should be reported to the client and the consultant is responsible for modification of design if necessary and no extra payment will be paid to the consultant.

 

 

A.1.2   Design and Contract Administration Services beyond the following limits will be provided by the consultant as a change in services in accordance with paragraphs C:

 

(a)    Up to 2 (two) revision of preliminary designs

(b)   Up to 1 (one) reviews of each shop drawing, product data item, sample and similar submittal of the contractor.

 

(a)        Up to 2 (two) visits per month to the site by the Architects over the duration of the project during construction. [Minimum mandatory visits]

(b)        Up to 2 (two) inspections for any portion of the work to determine whether such portion of the work is substantially complete in accordance with the requirements of the contract documents. [Minimum mandatory visits]

(c)        Up to 2 (two) inspection of the work during the defect liability period to review defects on request of client.

(d)       Up to 2 (two) inspection of the work to determine final completion.


 Architect
 Calvin Tsao
Architect  Project Co-Ordinator
 Michael Hsieh
 
 
 
 Bhutan  Pem Jason  pemjason@gmail.com
 
 
 
 Singapore Team co-Ordinators
Sen Chung 
 SG. Legal. Finance
 Shirley Ong
 
 
 
 

Hi Jason,

I am so sorry I overlooked this e-mail! You’re probably wondering what happened!

Sometimes there is just such an avalanche of messages – especially after a period of travel and absence from the office – that important messages fall through the crack. Please accept my sincerest apologies again.

 

Jason, I am forwarding the message to Calvin’s side so he can discuss with you scope of work, roles and responsibilities, etc. as well as the specifications he is interested in for the site survey.

 

Calvin has already assigned one of his architects to be the coordinator for this project. His name is Michael Hsieh. I am copying Michael on this message as well as Colette, Calvin’s personal assistant (and the best way to reach Calvin by e-mail).

 

I am also attaching the initial set of specifications for the project. This is very rough but it would bring you up to date on what has been discussed so far with Karma.

 

As we would need the site survey to be able to take any steps towards design, it would be great if you and Calvin’s side can discuss the site survey as a top priority in order to generate quotations for our review and the subsequent appointment of a surveyor for the job.

 

Please do include myself and Sen Chung – who will be taking over the liaison role from me – in your correspondence with Calvin’s side.Many thanks, Jason.

Wish  all good wishes,

Mary Ann

 

 From: pem gyaltsen [mailto:pemjason@gmail.com]
Sent: Friday, October 10, 2008 2:16 PM
To: Dr Mary Ann Tsao
Cc: calvin@calvintsao.com
Subject: summary of services

Dear Mary,

Please find attached brief description of services that I see would be needed from my side as local consulatants for the Senior Sangha Project.

The areas highlighted in yellow are part of the supervision or project management during actual execution of the works on site.

Calvin, please feel free to edit/chnage anything that you might want to.

Regards

jason