To-Do List
| Action Point | Owner | Due Date | Complete | Completion Date | Update |
|---|---|---|---|---|---|
| Circulate GREXdraft MOU | NTRC | May 30, 2011 | May 31, 2011 | ||
| Ross to provide switch and racks | Ross University | June 3, 2011 | IXP team to provide specifications | ||
| Marpin 2K4 Ltd t host facilities | Marpin 2K4 Ltd | June 3, 2011 | ISPs opted for a neutral locations. NTRC is in discussion with the Minister for a possible location within the Financial Centre | ||
| Service Providers to run fibre to Marpin 2K4 Ltd | Digicel; LIME; SAT | June 10, 2011 | No longer required because of location change | ||
| Configure Switch | PCH in collaboration with Marpin 2K4 - remote access enabled | June 10, 2011 |
Showing 5 items from page Action Items sorted by Due Date.