Room & Pillar
This method has evolved from
the older system of breast stoping with timbered supports, combined with random
6-m sq pullers, which was the system used thought Mosaboni mine until the early
1970’s.
For room and Pillar stoping,
a pilot raise is put up from one level to the next, following the hanging wall
contact. A wooden chute is installed at the lower level, together with a 2 drum
electric scraper winch. Leaving a still pillar of 6 m above the lower level,
and crown pillar of 4 m below the upper level, the side walls of the raise are
progressively stripped, using aitleg mounted jackhammers. After blasting, the
roof is secured and roofbolted, using 1.5 m x 20 mm dia torsteel cement grouted
bolts on a 1.2 mx 1.2 m staggered pattern, and the broken ore is scraped down
to the chute. Where or thickness, and therefore stope height, is insufficient
for the use of standard rockbolts, a two piece coupled bolt is employed.
Initially stope sizing was
such that topes were stripped out to 10 to m span. Leaving 3 m wide rib pillars
between one stope and the next. Rock mechanics studies, carried out partly with
the aid of CMRS, have enabled stopes to be widened to 15 m as the standard span
and there are plans to increase this yet again to 20 m in favorable districts.
Once the stope has been widened to full width, any ore in the floor is
progressively stripped until the footwall contact is reached. Room and pillar
stoping is generally used where the ore is between 1m and 4m thick. Ore extraction is about
65%.
| Horizontal cut & fill
Where the width of the
orebody and roof conditions permit, the ore is mined bya standard horizontal
mechanized cut and fill method. A stope is started with a pilot raise following
the footwall contact, and an initial stope drive above a still pillar.
Drilling of the back within
the stope may be carried out using arleg mounted jackhammers or using drills
mounted on Teledyne stope wagons. Mechanises loading is undertaken using 0.76
cub m LHDs.
Stope back and the hanging
walls are roof bolted at 1.5 m x 1.5 centres, the roof bolts grouted in over
their whole length. There is a tendency for the chlorite schist hanging wall to
slugh off for a few cms above the countact, and overall dilution of the ore
runs at about 15%.
Deslimed mill tailings are
used as backfill. At the Mosaboni mine these are sent underground via a 76 mm
dia. borehole; thence to the stopes through a 88 mm ida. seamless pipe.
Backfill for the Pathagora mine is also taken from he Mosaboni concentrator,
while that for Surda comes from the
nearby South bank concentraror. Fill for the Rakha mine is supplied from
the Rakha plant. AT present there is a shortfall of material for use in hand to
assess the availablility of higher percentages of deslimed tailings and sand
gathered from the Subbarnrekha bed to make up the balance required.
Stope orepasses and access
ladderways are built up through the filled zone out of 10mm thick curved steel
plantes welded together make continuous inclined cylinders of 1.6 m dia. These
provide excellent smooth walled conditions for the ventilation air flow, and
relatively low friction conditions to facilitate the sliding of ore down the
ore passes at the comparatively flast angle necessary, as dictated by the
configuration of the orebody. Where the ore is usually flat, the orepass may be
put in the footwall. | Post Pillar stoping
This method is a development
from horizontal cut and fill, and is used in cases where the width and / or
inclination of the orebody, or the condition of the hanging wall, or the
concentration of rock stresses, are such that the ordinary method of roof
bolting and fill would not give sufficient support in the stopes.
In the post pillar stoping
method, narrow (4 m sq) pillars are left in the ore at regular intervals (13 m
along the strike and 9 m across) so that in plan view they appear like a normal
chequer-pattern room and pillar working. The pillars thus give additional
strength to prevent hanging wall to foot wall closure after stoping while the
fill material surrounding the narrow pillars provides them with lateral support
and prevent them failing through buckling under load.
In some areas of surda,
Rakha and Mosaboni mines, where fractured conditions of the hanging wall are
encountered, cable bolting using cables upto 20 m long is also employed to
supplement roof bolting. 57 mm dia. holes, 10 m to 20 m long are drilled into
the hanging and back of stope at 1.9-2 m intervals. Two 16 mm dia. tensile
steel cables are inserted together with a plastic grouting tube and a small dia
“breathing” tube. The grouting tube is slowly withdrawn as the grout is pumped
in. In two of the post pillar stages larger (1.68 Cub. m) LHDs are in use.
Ores are drawn from stopes
chutes is hand trammed to ore passes leading down to one of the main haulage
levels
On the main haulage level,
trains of wagons hauled b 4 te / 8 te battery or diesel locaomotives of various
makes carry the ore to central grizzlies of the horizontal fixed-bar type, with
250 mm openings, beneath which are bunkers leading to skip pockets. Oversize,
material is broken by Teledyne electro-hydraykuc rock breakers. Broken ore is hoisted
to the surface by skips or cages. Most of the production from Moaboni mine is
taken up the main inclined shaft system – from No. 2 subincline to No.1
sub-incline and finally up the Main Shaft the multiple handling required
forming one of the main bottlenecks or increased production. The circular shaft
takes care of man and material winding and about 25% of ore hoisting. |