WOOD CHIP FACILITY
SCOPE OF WORK
|
Project Description |
Estimated Cost* |
|
Wood Chip System Inclusive
|
$360,000
|
|
General Conditions |
$100,00 |
|
Building Costs (30’wx50’l @ +/- $200/sf |
$300,00 |
|
Excavating and Site Costs (replace paving, site work around building and site grading as required) |
$100,000 |
|
Mechanical Costs (includes connection to existing services heating and ventilation in the new building, pumps, electrical and minimal controls) |
$150,000 |
|
Underground Piping Costs (500ft x +/- $150/lf |
$75,000 |
|
Sub-Total |
$1,085,000 |
|
Estimating Contingency 5% |
$54,250 |
|
Sub-Total |
$1,139,250 |
|
Mark Up 10% |
$113,925 |
|
Bond 2% |
$22, 785 |
|
Construction Total |
$1,275,960 |
|
Project Contingency |
$102, 077 |
|
Engineering and Permitting Fees (Architectural, Engineering, Air Modeling, Site and Permits) |
$190,000 |
|
TOTAL COST |
$1,568,037 |
*based on 2009 values without escalation rate |