What facilities will you have to serve the expansion of the school to Mattayom 6?

โพสต์‎‎20 ต.ค. 2551, 21:37‎‎โดยDavid Goldsack   [ อัปเดต ‎‎20 ต.ค. 2551, 21:53‎‎ ]

REPS has final approval for its Phase 2 building which will accommodate the Mathyom school in the coming years.  Building work on the second school house, a covered multi-purpose sports area and new changing rooms will begin in November 2008 for completion in April 2009.  Phase 3 comprises a third school house and further sports facilities and is envisaged to start in 2010.