Timeline for Project

Item Number
1 Task 1 – Research Management & Technology Status Assessment
2 Establish advisory committee
3 Meet with partners
4 Firm up commitments
5 Seek new sponsors
6 Set up communication center (coordinate with OOC)
7 Prepare reporting schedule, model with OOC (Office of Communications
8 Create Project Gantt Chart, detailed, with milestones, deadlines)
9 Establish relationship with similar research program
10 Compile similar information from other sources
11 Establish local community link (geographically, technology-wise) 
12 Hire graduate students
13 Hire contractors
14 Schedule projects activities on site – meet with subcontractor on site
15 Arrange GPRI Project - U of Wyoming
16 Task 2 – Early Economic, Market, and Environmental Studies.
17 Meet with TTI officials, study transportation, construction, civil engineering operations with related tasks
18 Prepare matrix of costs to construct roads (West Texas, New Mexico 
19 Work with DR contest winners to ascertain feasibility of concept prototype study
20 Identify industry sponsor to serve on advisory committee, set strategy for field implementation (John Rogers)
21 Prepare Technology Assessment Report
22 Task 3 – Technology Transfer.
23 have RPSEA - Pecos kickoff meeting
24 Establish communications link (website)
25 Establish IP study team for new operational practices, 
26 Prepare briefing document for PTTC
27 GPRI Project - kickoff meeting Coordinate with U of Wyomin
28 Task 4 – Planning Field Demonstration - Development, Testing and Deployment.
29 Prepare site,
30 Find contractor for road prep
31 Identify site of test
32 Arrange construction, 
33 Prepare needed contracts
34 Establish Matrix of performance
35 Plan U of Wyoming field test
36 Visit to U Wyoming to discuss field concept test
37 Task 5 Mobilize Equipment to Test Site and Construct Test Tracks.
38 Set priority testing
39 Set standards
40 Arrange for monitoring
41 Establish U of Wyoming GPRI project
42 Task 6 Operations: Performance, Monitoring and Demonstrations.
43 Establish monitoring schedule
44 Set up internet based monitoring, Matrix of performance, data analysis
45 Set up performance standards
46 Create schedule of visits by sponsors
47 Monitor roads
48 Monitor U Woming site
49 Prepare monitoring reports
50 Prepare demonstration reports
51 Plan for conclusion or for continuation of testing 
52 Shut down project, and demobilize or phase project into Phase II 
53 Task 7 – Analyze Performance of Low-Impact Systems.
54 Matrix of performance, data analysis
55 Compare with standard systems
56 Analyze GPRI Project
57 Task 8 – Update Economic Analysis and Finalize Project Field Testing – Field Demonstrations
58 Plan follow up remediation study.
59 Seek funding
60 Write technical publication
61 Plan wrapup of RPSEA project Phase 1
62 Task 9 – Final Report.
63 Prepare final draft
64 Get approval for final
65 Prepare final report
66 Prepare GPRI Project Final Report