BMC New Facility

  The drawings for the new BMC permanent facility have been released by the architect.  As we receive more information and images, we will post them here.  Please keep in mind that the design of the building may change during the construction process due to budget constraints, logistical challenges, and other factors.  Check back often for new content!

 

External View of New BMC Building

 

Groundbreaking Ceremony

 Posted 7/24/08
 
TENTATIVE - August 20th at 10:00 a.m.
 
A new post will be made here and to the Yahoo Group with specifics such as the final start time, parking instructions, etc. This event will be well attended by local and state level representatives, college staff, community members, and of course the Brashier Middle College family. We hope that you can join us as we show our excitement for the future and gratitude for outside assistance.

UPDATE:

The Groundbreaking Ceremony for the new facility was a great celebration of all the hard work and effort everyone has put into making our new facility a reality.  Thanks to everyone who attended and showed your dedication to our school! 



UPDATE #2:

The Greenville News has an article about the Groundbreaking Ceremony.  You can find it here.
 

Building Update

Posted 7/24/08
 
We have crossed nearly all of the hurdles facing our new facility. The contracts have been issued to Freeman and Major Architects and Triangle Construction. Although they have not started the site work, the design work is advancing quickly and completion should be early July 2009.  We know you will be excited with the design above developed by Allen Freeman.
 

Newspaper Article

Posted 8/14/08
 

The Greenville News is running an article online about the new building and groundbreaking ceremony on August 20th (see above).  Check out the article here:

Charter School to Break Ground

Construction Starts!

Posted 9/18/08
 
The site preparation has begun - check out the pictures of the construction process getting underway:


Site Preparations Continue...

Posted 9/25/08
 
The site has developed quite a bit since last week - here's the slideshow:


Site Excavation

Posted 10/6/08
 
We were busy last week and missed our normal Thursday visit to the site, but were shocked to see how much has taken place since our last slideshow - here are the pictures:



NOTICE:  Gravel Road CLOSED COMPLETELY

Posted 10/6/08

The gravel road is not only CLOSED, but GONE!  Please use the main entrance to the college for all traffic.

Foundation Preparation

Posted 10/15/08
 
Our visit was once again a bit late, but we were happy to see how much had been done:

 
 

First Foundations

Posted 10/26/08
 
The base of the retaining wall, and the first foundation "footings" have been poured:
 


Retaining Wall Construction

Posted 11/1/08
 
Construction of the retaining wall has started, and progressed quickly:



Foundation Work Continues

Posted 11/9/08
 
Since we couldn't visit the site this week, Jimmy the Triangle Foreman emailed us some - thanks Jimmy!



Steel Arrives

Posted 11/24/08
 
Once again, Jimmy took time out of his busy day to send not one but two batches of pictures - thank you!  The first load of steel arrives onsite, and foundation work continues on...



Steelwork Begins

Posted 12/4/08
 
I apologize for being behind in the updates - so here's two slideshows to catch us up.  Massive changes have occurred; parts of the steel skeleton of the building are in place, and are now visible from the entire campus!




UPDATE:

The pictures are coming in faster than I can post them - the pace of the work is amazing!  These were taken the afternoon of 12/4/08:


Water and Sewer Lines Installed

Posted 12/16/08
 
The changes aren't as dramatic this time as seeing the steel go up, but even the seemingly little ones are exciting!  The water and sewer lines have been installed, and the upper level floors are taking shape as steel decking is laid in place.  Thanks again to Jimmy, the Triangle foreman, for the pictures.


Long Time, No Updates!

Posted 1/22/09

Sorry to have not posted for so long - to make up for it, here's 3 slideshows of the latest updates:


Rough Plumbing

Taken 12/24/08
 
The rough plumbing for the lower floor is being placed, and some of the upper floor steel decking is installed.


Steelwork Progress 1

Taken 1/10/09
 
The building continues to grow as more steel is put into place.


Steelwork Progress 2

Taken 1/22/09
 
Details are beginning to emerge on the building, such as the cafeteria window structure and one of the roof cupolas.


Interior Framing Begins

Posted 2/2/09
 
The first truckload of light-gauge steel arrives, and work begins on the interior walls. The steel for the gym has been put in place as well.


Interior Framing Continues

Posted 2/10/09
 
The exterior framing on the second floor continues, while the first floor is readied to be poured. Internal elements such as ventilation ducts are being placed.


Interior Walls Placed

Posted 2/17/09
 
The upstairs interior walls have been framed with light gauge steel, the first floor concrete has been poured, and part of the roof has been installed.



Interior Work Progress

Posted 2/25/09
 
The interior elements of the new building are coming along quickly, with more framing, external paneling being placed, and further concrete work.



SPECIAL - Sneak Peak!

Posted 2/26/09
 
We got to take a sneak peek at the new facility - the progress is amazing, and the scale of every room and common area is overwhelming!


Snow Day!

Posted 3/19/09
 
Even unfinished, our new building looks nice in the snow. Hopefully this will be the last time we see snow inside the building!


Drywall Begins

Posted 4/1/09
 
Insulation and drywall has been placed in the building's interior, with the hallways and rooms taking shape. Exterior elements like the window framing have been added as well.



BMC Staff Visit New Building

Posted 4/21/09
 
The BMC Staff got to tour the new building, seeing the construction progress, and finding their new rooms.



Brickwork and Interior Progress

Posted 4/21/09
 
The brick has started to rise on the exterior of the building as the interior spaces are being finished...



Parking Lot Poured

Posted 7/14/09
 
The parking lot for the new building is being poured and paved. This is a good news to all since the rain has kept this element from being completed!



Latest Exterior Pictures

Posted 7/14/09
 
The exterior of the building is almost complete, with minor details being finished. The parking lot has already had lines painted, and even some landscaping has begun.